Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | TON | 1 | $62.00 | $62.00 to $62.00 | Bids
|
| concrete pavement | S Y | 1 | $6.20 | $6.20 to $6.20 | Bids
|
| flexible base | C Y | 2 | $58.40 | $26.80 to $90.00 | |
| inlet headwall | EACH | 2 | $175.00 | $150.00 to $200.00 | |
| lime cement stabilization | ACRE | 1 | $1,000.00 | $1,000.00 to $1,000.00 | Bids
|
| lime cement stabilization | LB | 1 | $0.84 | $0.84 to $0.84 | Bids
|
| lime cement stabilization | LS | 1 | $1,500.00 | $1,500.00 to $1,500.00 | Bids
|
| lime cement stabilization | MGAL | 2 | $3,030.00 | $560.00 to $5,500.00 | |
| lime cement stabilization | S Y | 1 | $2.40 | $2.40 to $2.40 | Bids
|
| lime cement stabilization | SQ YD | 2 | $1.85 | $1.70 to $2.00 |
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.