Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | TON | 1 | $70.40 | $70.40 to $70.40 | Bids
|
| concrete pavement | S Y | 1 | $99.07 | $99.07 to $99.07 | Bids
|
| curb gutter | L F | 2 | $7.71 | $2.87 to $12.55 | |
| fire hydrant | EACH | 1 | $8,950.00 | $8,950.00 to $8,950.00 | Bids
|
| flexible base | C Y | 2 | $50.00 | $40.00 to $60.00 | |
| inlet headwall | EACH | 4 | $1,078.00 | $500.00 to $4,500.00 | |
| lime cement stabilization | LS | 2 | $1,200.00 | $100.00 to $2,300.00 | |
| lime cement stabilization | S Y | 1 | $2.50 | $2.50 to $2.50 | Bids
|
| water service | EACH | 1 | $1,175.00 | $1,175.00 to $1,175.00 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.