Site-work prices, Rock County, MN
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| concrete pavement | S Y | 1 | $63.24 | $63.24 to $63.24 | Bids
|
| curb gutter | EACH | 1 | $475.00 | $475.00 to $475.00 | Bids
|
| fire hydrant | EACH | 1 | $8,132.00 | $8,132.00 to $8,132.00 | Bids
|
| flexible base | C Y | 1 | $35.00 | $35.00 to $35.00 | Bids
|
| inlet headwall | EACH | 1 | $600.15 | $600.15 to $600.15 | Bids
|
| lime cement stabilization | LS | 1 | $2,500.00 | $2,500.00 to $2,500.00 | Bids
|
| lime cement stabilization | MGAL | 2 | $437.50 | $425.00 to $450.00 | |
| lime cement stabilization | S Y | 1 | $1.47 | $1.47 to $1.47 | Bids
|
| manhole | EACH | 1 | $28,900.00 | $28,900.00 to $28,900.00 | Bids
|
| sewer service | L F | 1 | $92.50 | $92.50 to $92.50 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.