Site-work prices, Otter Tail County, MN
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| concrete pavement | S Y | 3 | $110.00 | $86.90 to $123.26 | |
| curb gutter | L F | 3 | $56.03 | $26.30 to $100.00 | |
| fire hydrant | EACH | 1 | $7,508.78 | $7,508.78 to $7,508.78 | Bids
|
| flexible base | C Y | 4 | $40.67 | $39.50 to $55.00 | |
| inlet headwall | EACH | 1 | $600.00 | $600.00 to $600.00 | Bids
|
| lime cement stabilization | LB | 1 | $1.40 | $1.40 to $1.40 | Bids
|
| lime cement stabilization | LS | 3 | $12,000.00 | $5,500.00 to $19,500.00 | |
| lime cement stabilization | MGAL | 2 | $765.50 | $631.00 to $900.00 | |
| lime cement stabilization | S Y | 1 | $1.45 | $1.45 to $1.45 | Bids
|
| manhole | EACH | 2 | $1,681.00 | $1,630.00 to $1,732.00 | |
| sewer service | L F | 1 | $7.00 | $7.00 to $7.00 | Bids
|
| water service | L F | 1 | $8.00 | $8.00 to $8.00 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.