Site-work prices, Lincoln County, MN
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| curb gutter | L F | 2 | $29.38 | $14.00 to $44.75 | |
| fire hydrant | EACH | 1 | $7,000.00 | $7,000.00 to $7,000.00 | Bids
|
| fire hydrant | L F | 1 | $1,250.00 | $1,250.00 to $1,250.00 | Bids
|
| flexible base | C Y | 2 | $35.80 | $34.00 to $37.60 | |
| flexible base | TON | 1 | $31.35 | $31.35 to $31.35 | Bids
|
| inlet headwall | EACH | 1 | $700.00 | $700.00 to $700.00 | Bids
|
| lime cement stabilization | C Y | 1 | $55.00 | $55.00 to $55.00 | Bids
|
| lime cement stabilization | LS | 2 | $3,500.00 | $2,500.00 to $4,500.00 | |
| lime cement stabilization | MGAL | 2 | $425.00 | $425.00 to $425.00 | |
| lime cement stabilization | S Y | 1 | $1.53 | $1.53 to $1.53 | Bids
|
| sewer service | L F | 1 | $53.00 | $53.00 to $53.00 | Bids
|
| water service | EACH | 1 | $525.00 | $525.00 to $525.00 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.