Site-work prices, Itasca County, MN
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| curb gutter | L F | 1 | $40.00 | $40.00 to $40.00 | Bids
|
| flexible base | C Y | 3 | $43.50 | $35.50 to $73.00 | |
| lime cement stabilization | LB | 1 | $2.05 | $2.05 to $2.05 | Bids
|
| lime cement stabilization | LS | 1 | $6,000.00 | $6,000.00 to $6,000.00 | Bids
|
| lime cement stabilization | MGAL | 2 | $705.00 | $600.00 to $810.00 | |
| lime cement stabilization | S Y | 3 | $2.50 | $2.00 to $2.65 | |
| sidewalk | EACH | 1 | $3,030.00 | $3,030.00 to $3,030.00 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.