Site-work prices, Hubbard County, MN
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| flexible base | C Y | 5 | $25.55 | $23.00 to $37.50 | Bids
|
| lime cement stabilization | LB | 1 | $1.25 | $1.25 to $1.25 | Bids
|
| lime cement stabilization | LS | 4 | $4,250.00 | $1,200.00 to $7,386.65 | |
| lime cement stabilization | MGAL | 3 | $316.57 | $300.00 to $395.00 | |
| lime cement stabilization | S Y | 3 | $1.99 | $0.09 to $2.90 |
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.