Site-work prices, St. Landry County, LA

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON30$180.00$64.00 to $1,000.00
Bids
  • 2026-08-12 · LaDOTD · LA 10: PALMETTO - US 71 · $128.00 per TON · qty 18719.7 · bid tab
  • 2026-08-12 · LaDOTD · LA 10: PALMETTO - US 71 · $80.00 per TON · qty 297.2 · bid tab
  • 2026-08-12 · LaDOTD · LA 755-S: LA 755 - LA 91 · $191.38 per TON · qty 990.8 · bid tab
  • 2026-08-12 · LaDOTD · LA 755-S: LA 755 - LA 91 · $167.14 per TON · qty 2813.2 · bid tab
  • 2026-07-08 · LaDOTD · LA 104: 2.6 MI NW US 190 - US 190 · $64.00 per TON · qty 1555.4 · bid tab
  • 2026-07-08 · LaDOTD · LA 104: 2.6 MI NW US 190 - US 190 · $189.00 per TON · qty 9810.5 · bid tab
  • 2026-06-24 · LaDOTD · SOLID WASTE ROAD OVER BAYOU BOEUF · $312.00 per TON · qty 169.1 · bid tab
  • 2026-06-24 · LaDOTD · SOLID WASTE ROAD OVER BAYOU BOEUF · $400.00 per TON · qty 84.8 · bid tab
  • 2026-05-13 · LaDOTD · US 190: R-CUT AT LA 741 · $395.00 per TON · qty 74.8 · bid tab
  • 2026-05-13 · LaDOTD · US 190: R-CUT AT LA 741 · $179.00 per TON · qty 10551.0 · bid tab
(10 most recent of 30 shown; all in the Hubstake feed)
concrete pavementSQYD1$165.00$165.00 to $165.00
Bids
  • 2024-10-09 · LaDOTD · LA 31/LA 182: LA 742 - 0.355MI. N. LA 31 · $165.00 per SQYD · qty 59.6 · bid tab
curb gutterLNFT4$67.00$32.00 to $120.00
Bids
  • 2026-07-08 · LaDOTD · LA 104: 2.6 MI NW US 190 - US 190 · $79.00 per LNFT · qty 200.0 · bid tab
  • 2026-05-13 · LaDOTD · US 190: R-CUT AT LA 741 · $32.00 per LNFT · qty 3251.8 · bid tab
  • 2026-01-07 · LaDOTD · LA 13: EMER. CROSS DRAIN REPLACEMENT · $120.00 per LNFT · qty 65.0 · bid tab
  • 2024-10-09 · LaDOTD · LA 31/LA 182: LA 742 - 0.355MI. N. LA 31 · $55.00 per LNFT · qty 110.2 · bid tab
excavation embankmentCUYD11$45.00$15.00 to $360.00
Bids
  • 2026-08-12 · LaDOTD · LA 10: PALMETTO - US 71 · $15.00 per CUYD · qty 650.0 · bid tab
  • 2026-07-08 · LaDOTD · LA 104: 2.6 MI NW US 190 - US 190 · $32.00 per CUYD · qty 473.0 · bid tab
  • 2026-01-07 · LaDOTD · LA 13: EMER. CROSS DRAIN REPLACEMENT · $360.00 per CUYD · qty 15.0 · bid tab
  • 2025-06-25 · LaDOTD · LA 10 BRIDGES · $27.00 per CUYD · qty 10178.0 · bid tab
  • 2025-05-14 · LaDOTD · LA 178: W. JCT. LA 182 - E. JCT. LA 182 · $45.00 per CUYD · qty 1307.0 · bid tab
  • 2025-05-14 · LaDOTD · LA 343: LA 98 - LA 356 · $80.00 per CUYD · qty 1279.0 · bid tab
  • 2025-01-08 · LaDOTD · LA 359: LOCAL ROAD (BOLDEN)-LA 10 · $21.00 per CUYD · qty 1600.0 · bid tab
  • 2024-09-18 · LaDOTD · LA 10: LITTLE WAUKSHA BR - US 71 · $32.00 per CUYD · qty 7631.0 · bid tab
  • 2024-06-12 · LaDOTD · LA 3116: EUNICE REPAIRS · $90.00 per CUYD · qty 133.0 · bid tab
  • 2024-04-16 · LaDOTD · LA 10: EMER. CROSS DRAIN REPLACEMENT · $77.00 per CUYD · qty 250.0 · bid tab
(10 most recent of 11 shown; all in the Hubstake feed)
flexible baseSQYD6$46.00$20.00 to $54.00
Bids
  • 2026-08-12 · LaDOTD · LA 755-S: LA 755 - LA 91 · $37.03 per SQYD · qty 978.0 · bid tab
  • 2026-07-08 · LaDOTD · LA 104: 2.6 MI NW US 190 - US 190 · $20.00 per SQYD · qty 1710.3 · bid tab
  • 2026-06-24 · LaDOTD · SOLID WASTE ROAD OVER BAYOU BOEUF · $53.00 per SQYD · qty 639.6 · bid tab
  • 2026-05-13 · LaDOTD · US 190: R-CUT AT LA 741 · $42.00 per SQYD · qty 12047.5 · bid tab
  • 2025-06-25 · LaDOTD · LA 10 BRIDGES · $50.00 per SQYD · qty 9946.6 · bid tab
  • 2025-06-11 · LaDOTD · LA 10: BAYOU CARRON BRIDGE · $54.00 per SQYD · qty 3107.1 · bid tab
inlet headwallEACH8$70,751.73$45,000.00 to $110,000.00
Bids
  • 2026-08-12 · LaDOTD · LA 10: PALMETTO - US 71 · $55,000.00 per EACH · qty 2.0 · bid tab
  • 2026-08-12 · LaDOTD · LA 755-S: LA 755 - LA 91 · $88,824.45 per EACH · qty 2.0 · bid tab
  • 2026-08-12 · LaDOTD · LA 755-S: LA 755 - LA 91 · $66,503.45 per EACH · qty 2.0 · bid tab
  • 2026-07-08 · LaDOTD · LA 104: 2.6 MI NW US 190 - US 190 · $110,000.00 per EACH · qty 6.0 · bid tab
  • 2025-05-14 · LaDOTD · LA 178: W. JCT. LA 182 - E. JCT. LA 182 · $49,500.00 per EACH · qty 2.0 · bid tab
  • 2025-05-14 · LaDOTD · LA 343: LA 98 - LA 356 · $80,000.00 per EACH · qty 2.0 · bid tab
  • 2024-09-18 · LaDOTD · LA 10: LITTLE WAUKSHA BR - US 71 · $75,000.00 per EACH · qty 2.0 · bid tab
  • 2024-04-16 · LaDOTD · LA 10: EMER. CROSS DRAIN REPLACEMENT · $45,000.00 per EACH · qty 2.0 · bid tab
lime cement stabilizationSQYD19$11.00$2.25 to $16.33
Bids
  • 2026-08-12 · LaDOTD · LA 10: PALMETTO - US 71 · $15.00 per SQYD · qty 59692.0 · bid tab
  • 2026-08-12 · LaDOTD · LA 10: PALMETTO - US 71 · $11.00 per SQYD · qty 6933.0 · bid tab
  • 2026-08-12 · LaDOTD · LA 10: PALMETTO - US 71 · $4.75 per SQYD · qty 6933.0 · bid tab
  • 2026-08-12 · LaDOTD · LA 755-S: LA 755 - LA 91 · $6.75 per SQYD · qty 3400.0 · bid tab
  • 2026-08-12 · LaDOTD · LA 755-S: LA 755 - LA 91 · $11.81 per SQYD · qty 5822.0 · bid tab
  • 2026-07-08 · LaDOTD · LA 104: 2.6 MI NW US 190 - US 190 · $16.33 per SQYD · qty 32876.0 · bid tab
  • 2026-07-08 · LaDOTD · LA 104: 2.6 MI NW US 190 - US 190 · $12.70 per SQYD · qty 31166.0 · bid tab
  • 2026-06-24 · LaDOTD · SOLID WASTE ROAD OVER BAYOU BOEUF · $10.00 per SQYD · qty 640.0 · bid tab
  • 2025-06-11 · LaDOTD · LA 10: BAYOU CARRON BRIDGE · $10.00 per SQYD · qty 2973.5 · bid tab
  • 2025-05-14 · LaDOTD · LA 178: W. JCT. LA 182 - E. JCT. LA 182 · $12.50 per SQYD · qty 35884.0 · bid tab
(10 most recent of 19 shown; all in the Hubstake feed)
lime cement stabilizationTON7$369.87$300.00 to $420.00
Bids
  • 2026-08-12 · LaDOTD · LA 10: PALMETTO - US 71 · $420.00 per TON · qty 54.6 · bid tab
  • 2026-08-12 · LaDOTD · LA 755-S: LA 755 - LA 91 · $369.87 per TON · qty 48.19 · bid tab
  • 2026-06-24 · LaDOTD · SOLID WASTE ROAD OVER BAYOU BOEUF · $300.00 per TON · qty 24.48 · bid tab
  • 2025-06-11 · LaDOTD · LA 10: BAYOU CARRON BRIDGE · $300.00 per TON · qty 43.0 · bid tab
  • 2025-05-14 · LaDOTD · LA 178: W. JCT. LA 182 - E. JCT. LA 182 · $350.00 per TON · qty 169.0 · bid tab
  • 2025-05-14 · LaDOTD · LA 343: LA 98 - LA 356 · $415.00 per TON · qty 235.9 · bid tab
  • 2025-01-08 · LaDOTD · LA 359: LOCAL ROAD (BOLDEN)-LA 10 · $410.00 per TON · qty 125.85 · bid tab
manholeEACH13$1,300.00$471.00 to $29,150.00
Bids
  • 2026-08-12 · LaDOTD · LA 755-S: LA 755 - LA 91 · $13,538.34 per EACH · qty 1.0 · bid tab
  • 2026-07-08 · LaDOTD · LA 104: 2.6 MI NW US 190 - US 190 · $8,000.00 per EACH · qty 1.0 · bid tab
  • 2026-05-13 · LaDOTD · US 190: R-CUT AT LA 741 · $7,300.00 per EACH · qty 1.0 · bid tab
  • 2025-11-12 · LaDOTD · I-49: LA 3233 INTCHG LIGHTING (OPEL.) · $471.00 per EACH · qty 49.0 · bid tab
  • 2025-11-12 · LaDOTD · I-49: LA 3233 INTCHG LIGHTING (OPEL.) · $1,289.00 per EACH · qty 4.0 · bid tab
  • 2025-11-12 · LaDOTD · I-49: LA 3233 INTCHG LIGHTING (OPEL.) · $706.00 per EACH · qty 13.0 · bid tab
  • 2025-05-14 · LaDOTD · LA 178: W. JCT. LA 182 - E. JCT. LA 182 · $29,150.00 per EACH · qty 1.0 · bid tab
  • 2024-12-11 · LaDOTD · I-49: US 190 INTCHG LIGHTING (OPELOUSAS) · $1,250.00 per EACH · qty 4.0 · bid tab
  • 2024-12-11 · LaDOTD · I-49: US 190 INTCHG LIGHTING (OPELOUSAS) · $1,300.00 per EACH · qty 26.0 · bid tab
  • 2024-12-11 · LaDOTD · I-49: US 190 INTCHG LIGHTING (OPELOUSAS) · $750.00 per EACH · qty 27.0 · bid tab
(10 most recent of 13 shown; all in the Hubstake feed)

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.