| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 7 | $300.00 | $100.00 to $452.00 | Bids- 2026-09-15 · LaDOTD · LA 39: CROSS DRAIN REP'L 1800' N LA 46 · $300.00 per TON · qty 6.0 · bid tab
- 2024-11-13 · LaDOTD · LA 300: BAYOU LALOUTRE BRIDGE · $360.00 per TON · qty 466.3 · bid tab
- 2024-11-13 · LaDOTD · LA 300: BAYOU LALOUTRE BRIDGE · $360.00 per TON · qty 50.7 · bid tab
- 2024-11-13 · LaDOTD · LA 300: LA 39 - 2215 LA 300 · $100.00 per TON · qty 380.0 · bid tab
- 2024-11-13 · LaDOTD · LA 300: LA 39 - 2215 LA 300 · $140.00 per TON · qty 1125.4 · bid tab
- 2024-04-17 · LaDOTD · LA 46 @ WEINBERGER RD INTERSECTION · $260.00 per TON · qty 412.9 · bid tab
- 2024-04-17 · LaDOTD · LA 46 @ WEINBERGER RD INTERSECTION · $452.00 per TON · qty 332.1 · bid tab
|
| concrete pavement | SQYD | 3 | $121.00 | $104.00 to $121.00 | Bids- 2025-10-15 · LaDOTD · LA 39 PATCHING: NORTON AVE - PARIS RD · $104.00 per SQYD · qty 171.7 · bid tab
- 2024-04-17 · LaDOTD · LA 46 @ WEINBERGER RD INTERSECTION · $121.00 per SQYD · qty 1479.1 · bid tab
- 2024-04-17 · LaDOTD · LA 46 @ WEINBERGER RD INTERSECTION · $121.00 per SQYD · qty 1000.4 · bid tab
|
| curb gutter | LNFT | 5 | $60.00 | $18.00 to $70.00 | Bids- 2026-02-11 · LaDOTD · LA 39: W. JUDGE PEREZ DR. ENHANCEMENTS · $28.00 per LNFT · qty 299.1 · bid tab
- 2025-10-15 · LaDOTD · LA 39 PATCHING: NORTON AVE - PARIS RD · $18.00 per LNFT · qty 2746.0 · bid tab
- 2025-01-08 · LaDOTD · ST. BERNARD PEDESTRIAN IMPROVEMENTS · $60.00 per LNFT · qty 70.0 · bid tab
- 2024-12-11 · LaDOTD · JEAN LAFITTE PARKWAY SHARED USE PATH · $70.00 per LNFT · qty 96.0 · bid tab
- 2024-04-17 · LaDOTD · LA 46 @ WEINBERGER RD INTERSECTION · $65.00 per LNFT · qty 933.9 · bid tab
|
| excavation embankment | CUYD | 9 | $65.00 | $28.00 to $175.00 | Bids- 2026-09-15 · LaDOTD · LA 39: CROSS DRAIN REP'L 1800' N LA 46 · $175.00 per CUYD · qty 20.0 · bid tab
- 2026-02-11 · LaDOTD · LA 39: W. JUDGE PEREZ DR. ENHANCEMENTS · $95.00 per CUYD · qty 227.0 · bid tab
- 2025-10-15 · LaDOTD · LA 39 PATCHING: NORTON AVE - PARIS RD · $136.00 per CUYD · qty 9.0 · bid tab
- 2025-10-15 · LaDOTD · LA 39 PATCHING: NORTON AVE - PARIS RD · $70.00 per CUYD · qty 135.0 · bid tab
- 2024-12-11 · LaDOTD · JEAN LAFITTE PARKWAY SHARED USE PATH · $65.00 per CUYD · qty 716.0 · bid tab
- 2024-11-13 · LaDOTD · LA 300: BAYOU LALOUTRE BRIDGE · $52.00 per CUYD · qty 760.0 · bid tab
- 2024-11-13 · LaDOTD · LA 300: LA 39 - 2215 LA 300 · $65.00 per CUYD · qty 40.0 · bid tab
- 2024-04-17 · LaDOTD · LA 46 @ WEINBERGER RD INTERSECTION · $35.00 per CUYD · qty 205.0 · bid tab
- 2024-04-17 · LaDOTD · LA 46 @ WEINBERGER RD INTERSECTION · $28.00 per CUYD · qty 3579.0 · bid tab
|
| flexible base | CUYD | 1 | $68.00 | $68.00 to $68.00 | Bids- 2025-10-15 · LaDOTD · LA 39 PATCHING: NORTON AVE - PARIS RD · $68.00 per CUYD · qty 23.2 · bid tab
|
| flexible base | SQYD | 2 | $30.00 | $21.00 to $39.00 | Bids- 2024-04-17 · LaDOTD · LA 46 @ WEINBERGER RD INTERSECTION · $39.00 per SQYD · qty 2070.5 · bid tab
- 2024-04-17 · LaDOTD · LA 46 @ WEINBERGER RD INTERSECTION · $21.00 per SQYD · qty 3590.2 · bid tab
|
| lime cement stabilization | TON | 1 | $800.00 | $800.00 to $800.00 | Bids- 2024-12-11 · LaDOTD · JEAN LAFITTE PARKWAY SHARED USE PATH · $800.00 per TON · qty 1.66 · bid tab
|
| sidewalk | EACH | 1 | $1,450.00 | $1,450.00 to $1,450.00 | Bids- 2024-11-13 · LaDOTD · LA 300: LA 39 - 2215 LA 300 · $1,450.00 per EACH · qty 7.0 · bid tab
|