Site-work prices, Richland County, LA
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 8 | $202.50 | $127.00 to $400.00 | Bids- 2026-09-09 · LaDOTD · LA 132: LA 135 - US 425 · $235.00 per TON · qty 1200.5 · bid tab
- 2026-09-09 · LaDOTD · LA 132: LA 135 - US 425 · $148.00 per TON · qty 13476.2 · bid tab
- 2026-06-10 · LaDOTD · LITTLE ROAD OVER CREEK · $400.00 per TON · qty 100.6 · bid tab
- 2026-06-10 · LaDOTD · LITTLE ROAD OVER CREEK · $300.00 per TON · qty 190.7 · bid tab
- 2024-09-18 · LaDOTD · LA 17: FRANKLIN P/L - RUNDELL LP · $170.00 per TON · qty 11641.1 · bid tab
- 2024-09-18 · LaDOTD · LA 17: FRANKLIN P/L - RUNDELL LP · $170.00 per TON · qty 491.0 · bid tab
- 2024-08-28 · LaDOTD · LA 133: LA 15 - US 80 · $127.00 per TON · qty 21617.2 · bid tab
- 2024-08-28 · LaDOTD · LA 133: LA 15 - US 80 · $241.00 per TON · qty 2665.5 · bid tab
|
| curb gutter | LNFT | 1 | $60.00 | $60.00 to $60.00 | Bids- 2026-09-09 · LaDOTD · LA 132: LA 135 - US 425 · $60.00 per LNFT · qty 17.0 · bid tab
|
| excavation embankment | CUYD | 4 | $23.50 | $22.00 to $40.00 | Bids- 2026-09-09 · LaDOTD · LA 132: LA 135 - US 425 · $22.00 per CUYD · qty 572.0 · bid tab
- 2026-06-10 · LaDOTD · LITTLE ROAD OVER CREEK · $22.00 per CUYD · qty 1247.0 · bid tab
- 2024-09-18 · LaDOTD · LA 17: FRANKLIN P/L - RUNDELL LP · $25.00 per CUYD · qty 663.0 · bid tab
- 2024-08-28 · LaDOTD · LA 133: LA 15 - US 80 · $40.00 per CUYD · qty 2009.0 · bid tab
|
| flexible base | SQYD | 1 | $64.00 | $64.00 to $64.00 | Bids- 2026-06-10 · LaDOTD · LITTLE ROAD OVER CREEK · $64.00 per SQYD · qty 940.9 · bid tab
|
| lime cement stabilization | SQYD | 2 | $14.50 | $13.00 to $16.00 | Bids- 2026-09-09 · LaDOTD · LA 132: LA 135 - US 425 · $16.00 per SQYD · qty 59303.0 · bid tab
- 2026-06-10 · LaDOTD · LITTLE ROAD OVER CREEK · $13.00 per SQYD · qty 940.9 · bid tab
|
| lime cement stabilization | TON | 1 | $500.00 | $500.00 to $500.00 | Bids- 2026-06-10 · LaDOTD · LITTLE ROAD OVER CREEK · $500.00 per TON · qty 13.34 · bid tab
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.