| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 12 | $224.50 | $131.00 to $700.00 | Bids- 2025-12-10 · LaDOTD · US 84: OLLA FIELD RD - W. JCT. LA 772 · $131.00 per TON · qty 12058.9 · bid tab
- 2025-12-10 · LaDOTD · US 84: OLLA FIELD RD - W. JCT. LA 772 · $131.00 per TON · qty 922.7 · bid tab
- 2025-10-15 · LaDOTD · LA 771: LA 503 - END OF MAINTENANCE · $142.00 per TON · qty 10116.7 · bid tab
- 2025-10-15 · LaDOTD · LA 771: LA 503 - END OF MAINTENANCE · $350.00 per TON · qty 334.3 · bid tab
- 2025-09-10 · LaDOTD · US 84: JCT. US 165 - OLLA FIELD RD. · $249.00 per TON · qty 514.5 · bid tab
- 2025-09-10 · LaDOTD · US 84: JCT. US 165 - OLLA FIELD RD. · $140.00 per TON · qty 15853.2 · bid tab
- 2025-06-11 · LaDOTD · LA 3104 & LA 778 ASPHALT OVERLAYS · $262.00 per TON · qty 2567.9 · bid tab
- 2025-06-11 · LaDOTD · LA 3104 & LA 778 ASPHALT OVERLAYS · $150.00 per TON · qty 5573.4 · bid tab
- 2025-03-06 · LaDOTD · OLLA INTERSECTION IMPROVEMENTS · $700.00 per TON · qty 25.0 · bid tab
- 2025-03-06 · LaDOTD · OLLA INTERSECTION IMPROVEMENTS · $270.00 per TON · qty 501.4 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed) |
| excavation embankment | CUYD | 6 | $18.00 | $11.00 to $150.00 | Bids- 2025-12-10 · LaDOTD · US 84: OLLA FIELD RD - W. JCT. LA 772 · $150.00 per CUYD · qty 20.0 · bid tab
- 2025-10-15 · LaDOTD · LA 771: LA 503 - END OF MAINTENANCE · $22.00 per CUYD · qty 756.0 · bid tab
- 2025-09-10 · LaDOTD · US 84: JCT. US 165 - OLLA FIELD RD. · $18.00 per CUYD · qty 8.0 · bid tab
- 2025-06-11 · LaDOTD · LA 3104 & LA 778 ASPHALT OVERLAYS · $18.00 per CUYD · qty 384.0 · bid tab
- 2025-03-06 · LaDOTD · OLLA INTERSECTION IMPROVEMENTS · $11.00 per CUYD · qty 200.0 · bid tab
- 2025-02-12 · LaDOTD · US 84: UP RR OVERPASS REPLACEMENT (HBI) · $18.00 per CUYD · qty 44348.0 · bid tab
|
| flexible base | SQYD | 2 | $76.50 | $46.00 to $107.00 | Bids- 2025-03-06 · LaDOTD · OLLA INTERSECTION IMPROVEMENTS · $107.00 per SQYD · qty 1121.4 · bid tab
- 2025-02-12 · LaDOTD · US 84: UP RR OVERPASS REPLACEMENT (HBI) · $46.00 per SQYD · qty 7231.9 · bid tab
|
| inlet headwall | CUYD | 1 | $2,900.00 | $2,900.00 to $2,900.00 | Bids- 2025-06-11 · LaDOTD · LA 3104 & LA 778 ASPHALT OVERLAYS · $2,900.00 per CUYD · qty 7.26 · bid tab
|
| lime cement stabilization | SQYD | 2 | $8.88 | $4.00 to $13.75 | Bids- 2025-10-15 · LaDOTD · LA 771: LA 503 - END OF MAINTENANCE · $13.75 per SQYD · qty 54048.5 · bid tab
- 2025-02-12 · LaDOTD · US 84: UP RR OVERPASS REPLACEMENT (HBI) · $4.00 per SQYD · qty 7231.0 · bid tab
|
| lime cement stabilization | TON | 1 | $310.00 | $310.00 to $310.00 | Bids- 2025-02-12 · LaDOTD · US 84: UP RR OVERPASS REPLACEMENT (HBI) · $310.00 per TON · qty 102.52 · bid tab
|