Site-work prices, Bienville County, LA

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON6$175.00$95.00 to $226.50
Bids
  • 2026-01-14 · LaDOTD · US 80 & LA 9: LA 154 TO I-20 · $95.00 per TON · qty 1543.9 · bid tab
  • 2026-01-14 · LaDOTD · US 80 & LA 9: LA 154 TO I-20 · $150.00 per TON · qty 29891.9 · bid tab
  • 2024-12-11 · LaDOTD · LA 516: POLAND BRANCH BRIDGE · $200.00 per TON · qty 511.7 · bid tab
  • 2024-12-11 · LaDOTD · LA 516: POLAND BRANCH BRIDGE · $220.00 per TON · qty 95.0 · bid tab
  • 2024-10-09 · LaDOTD · US 371: RED RIVER P/L - WEBSTER P/L · $148.75 per TON · qty 73367.3 · bid tab
  • 2024-10-09 · LaDOTD · US 371: RED RIVER P/L - WEBSTER P/L · $226.50 per TON · qty 716.5 · bid tab
curb gutterLNFT1$100.00$100.00 to $100.00
Bids
  • 2026-01-14 · LaDOTD · US 80 & LA 9: LA 154 TO I-20 · $100.00 per LNFT · qty 108.0 · bid tab
excavation embankmentCUYD2$42.12$40.00 to $44.25
Bids
  • 2026-01-14 · LaDOTD · US 80 & LA 9: LA 154 TO I-20 · $40.00 per CUYD · qty 5850.0 · bid tab
  • 2024-10-09 · LaDOTD · US 371: RED RIVER P/L - WEBSTER P/L · $44.25 per CUYD · qty 9026.0 · bid tab
flexible baseSQYD1$37.00$37.00 to $37.00
Bids
  • 2024-12-11 · LaDOTD · LA 516: POLAND BRANCH BRIDGE · $37.00 per SQYD · qty 2294.1 · bid tab
lime cement stabilizationSQYD1$6.00$6.00 to $6.00
Bids
  • 2024-12-11 · LaDOTD · LA 516: POLAND BRANCH BRIDGE · $6.00 per SQYD · qty 1147.0 · bid tab
lime cement stabilizationTON1$400.00$400.00 to $400.00
Bids
  • 2024-12-11 · LaDOTD · LA 516: POLAND BRANCH BRIDGE · $400.00 per TON · qty 16.26 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.