Site-work prices, Assumption County, LA

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON6$176.50$105.00 to $225.00
Bids
  • 2025-09-10 · LaDOTD · LA 662: LA 182 - TERREBONNE P/L · $105.00 per TON · qty 1176.2 · bid tab
  • 2025-09-10 · LaDOTD · LA 662: LA 182 - TERREBONNE P/L · $105.00 per TON · qty 39621.7 · bid tab
  • 2024-07-10 · LaDOTD · LA 431: VILLAR CANAL AND DRAINAGE BRIDGES · $225.00 per TON · qty 344.9 · bid tab
  • 2024-07-10 · LaDOTD · LA 431: VILLAR CANAL AND DRAINAGE BRIDGES · $155.00 per TON · qty 1716.1 · bid tab
  • 2024-05-08 · LaDOTD · LA 308: LA 1011 - FRANKLIN AVE · $220.00 per TON · qty 281.2 · bid tab
  • 2024-05-08 · LaDOTD · LA 308: LA 1011 - FRANKLIN AVE · $198.00 per TON · qty 3257.3 · bid tab
curb gutterLNFT1$50.00$50.00 to $50.00
Bids
  • 2024-07-10 · LaDOTD · LA 431: VILLAR CANAL AND DRAINAGE BRIDGES · $50.00 per LNFT · qty 23.0 · bid tab
excavation embankmentCUYD4$43.50$25.00 to $150.00
Bids
  • 2025-09-10 · LaDOTD · LA 662: LA 182 - TERREBONNE P/L · $150.00 per CUYD · qty 134.0 · bid tab
  • 2024-07-10 · LaDOTD · LA 431: VILLAR CANAL AND DRAINAGE BRIDGES · $32.00 per CUYD · qty 6717.0 · bid tab
  • 2024-05-08 · LaDOTD · LA 308: LA 1011 - FRANKLIN AVE · $55.00 per CUYD · qty 1159.0 · bid tab
  • 2024-02-14 · LaDOTD · PEAR ST AT LA 1: DRAINAGE · $25.00 per CUYD · qty 4722.0 · bid tab
inlet headwallEACH1$39,000.00$39,000.00 to $39,000.00
Bids
  • 2024-02-14 · LaDOTD · PEAR ST AT LA 1: DRAINAGE · $39,000.00 per EACH · qty 1.0 · bid tab
lime cement stabilizationSQYD2$7.50$3.00 to $12.00
Bids
  • 2025-09-10 · LaDOTD · LA 662: LA 182 - TERREBONNE P/L · $12.00 per SQYD · qty 161289.0 · bid tab
  • 2025-09-10 · LaDOTD · LA 662: LA 182 - TERREBONNE P/L · $3.00 per SQYD · qty 77339.0 · bid tab
lime cement stabilizationTON1$360.00$360.00 to $360.00
Bids
  • 2025-09-10 · LaDOTD · LA 662: LA 182 - TERREBONNE P/L · $360.00 per TON · qty 1096.3 · bid tab
manholeEACH1$15,500.00$15,500.00 to $15,500.00
Bids
  • 2024-02-14 · LaDOTD · PEAR ST AT LA 1: DRAINAGE · $15,500.00 per EACH · qty 3.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.