Site-work prices, Mccracken County, KY

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON34$105.00$7.50 to $175.00
Bids
  • 2026-09-03 · KYTC · 26-2134 · $86.00 per TON · qty 520.0 · bid tab
  • 2026-09-03 · KYTC · 26-2134 · $86.00 per TON · qty 3300.0 · bid tab
  • 2026-05-21 · KYTC · 26-4512 · $115.00 per TON · qty 255.0 · bid tab
  • 2026-05-21 · KYTC · 26-4512 · $120.00 per TON · qty 34.0 · bid tab
  • 2026-05-21 · KYTC · 26-4512 · $120.00 per TON · qty 1537.0 · bid tab
  • 2026-05-21 · KYTC · 26-4512 · $7.50 per TON · qty 3762.0 · bid tab
  • 2026-05-21 · KYTC · 26-4512 · $120.00 per TON · qty 2692.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $110.00 per TON · qty 1788.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $110.00 per TON · qty 20.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $100.00 per TON · qty 3083.0 · bid tab
(10 most recent of 34 shown; all in the Hubstake feed)
curb gutterLF6$110.00$16.30 to $189.67
Bids
  • 2026-05-21 · KYTC · 26-4512 · $110.00 per LF · qty 978.0 · bid tab
  • 2026-05-21 · KYTC · 26-4512 · $110.00 per LF · qty 2723.0 · bid tab
  • 2026-05-21 · KYTC · 26-4512 · $110.00 per LF · qty 3566.0 · bid tab
  • 2025-12-11 · KYTC · 25-1012 · $16.30 per LF · qty 2870.0 · bid tab
  • 2025-07-24 · KYTC · 25-2311 · $66.00 per LF · qty 546.0 · bid tab
  • 2025-07-24 · KYTC · 25-2311 · $189.67 per LF · qty 112.0 · bid tab
excavation embankmentCUYD5$40.00$11.93 to $66.38
Bids
  • 2026-05-21 · KYTC · 26-4512 · $40.00 per CUYD · qty 5439.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $38.25 per CUYD · qty 2723.0 · bid tab
  • 2025-12-11 · KYTC · 25-1012 · $11.93 per CUYD · qty 351990.0 · bid tab
  • 2025-12-11 · KYTC · 25-1012 · $66.38 per CUYD · qty 3100.0 · bid tab
  • 2025-12-11 · KYTC · 25-1012 · $60.00 per CUYD · qty 465.0 · bid tab
flexible baseTON2$41.45$34.00 to $48.90
Bids
  • 2026-04-23 · KYTC · 26-4505 · $48.90 per TON · qty 3735.0 · bid tab
  • 2025-12-11 · KYTC · 25-1012 · $34.00 per TON · qty 13863.0 · bid tab
inlet headwallEACH12$7,031.95$1,754.15 to $12,900.00
Bids
  • 2026-05-21 · KYTC · 26-4512 · $12,900.00 per EACH · qty 1.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $9,711.21 per EACH · qty 5.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $8,221.60 per EACH · qty 1.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $6,938.91 per EACH · qty 2.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $9,300.09 per EACH · qty 11.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $6,806.68 per EACH · qty 2.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $2,700.98 per EACH · qty 1.0 · bid tab
  • 2025-12-11 · KYTC · 25-1012 · $7,125.00 per EACH · qty 9.0 · bid tab
  • 2025-12-11 · KYTC · 25-1012 · $1,754.15 per EACH · qty 4.0 · bid tab
  • 2025-12-11 · KYTC · 25-1012 · $3,877.57 per EACH · qty 2.0 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed)
lime cement stabilizationSQYD1$5.65$5.65 to $5.65
Bids
  • 2025-12-11 · KYTC · 25-1012 · $5.65 per SQYD · qty 18877.0 · bid tab
manholeEACH6$1,837.50$825.00 to $54,000.00
Bids
  • 2026-05-21 · KYTC · 26-4512 · $1,750.00 per EACH · qty 17.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $54,000.00 per EACH · qty 1.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $1,500.00 per EACH · qty 8.0 · bid tab
  • 2025-12-11 · KYTC · 25-1012 · $2,632.67 per EACH · qty 1.0 · bid tab
  • 2024-07-18 · KYTC · 24-2153 · $825.00 per EACH · qty 1.0 · bid tab
  • 2024-07-18 · KYTC · 24-2153 · $1,925.00 per EACH · qty 3.0 · bid tab
storm pipe 15-inchLF1$62.79$62.79 to $62.79
Bids
  • 2026-04-23 · KYTC · 26-4505 · $62.79 per LF · qty 387.0 · bid tab
storm pipe 18-inchLF4$159.66$87.61 to $295.00
Bids
  • 2026-05-21 · KYTC · 26-4512 · $295.00 per LF · qty 6.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $210.96 per LF · qty 45.0 · bid tab
  • 2026-04-23 · KYTC · 26-4505 · $108.36 per LF · qty 1263.0 · bid tab
  • 2025-12-11 · KYTC · 25-1012 · $87.61 per LF · qty 317.0 · bid tab
storm pipe 24-inchLF1$110.30$110.30 to $110.30
Bids
  • 2025-12-11 · KYTC · 25-1012 · $110.30 per LF · qty 53.0 · bid tab
storm pipe 30-inchLF1$133.29$133.29 to $133.29
Bids
  • 2025-12-11 · KYTC · 25-1012 · $133.29 per LF · qty 188.0 · bid tab
water main (diameter not stated)LF2$0.40$0.30 to $0.50
Bids
  • 2026-05-21 · KYTC · 26-4512 · $0.50 per LF · qty 1035.0 · bid tab
  • 2025-07-24 · KYTC · 25-2311 · $0.30 per LF · qty 28512.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.