Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON28$113.30$1.00 to $700.00
Bids
  • 2026-03-18 · KDOT · 526032131 · $113.25 per TON · qty 890.0 · bid tab
  • 2026-03-18 · KDOT · 526032131 · $121.00 per TON · qty 615.0 · bid tab
  • 2025-11-19 · KDOT · 525116141 · $110.50 per TON · qty 7325.0 · bid tab
  • 2025-11-19 · KDOT · 525116141 · $1.50 per TON · qty 20900.0 · bid tab
  • 2025-11-19 · KDOT · 525116141 · $700.00 per TON · qty 55.0 · bid tab
  • 2025-11-19 · KDOT · 525116141 · $142.00 per TON · qty 1400.0 · bid tab
  • 2025-11-19 · KDOT · 525116141 · $108.75 per TON · qty 13575.0 · bid tab
  • 2025-11-19 · KDOT · 525116151 · $101.50 per TON · qty 5550.0 · bid tab
  • 2025-11-19 · KDOT · 525116151 · $1.25 per TON · qty 30300.0 · bid tab
  • 2025-11-19 · KDOT · 525116151 · $700.00 per TON · qty 79.0 · bid tab
(10 most recent of 28 shown; all in the Hubstake feed)
concrete pavementEACH2$1.00$1.00 to $1.00
Bids
  • 2024-11-20 · KDOT · 524112121 · $1.00 per EACH · qty 1.0 · bid tab
  • 2024-11-20 · KDOT · 524112121 · $1.00 per EACH · qty 1.0 · bid tab
concrete pavementSQYD22$119.40$60.00 to $485.23
Bids
  • 2026-03-18 · KDOT · 526032131 · $98.65 per SQYD · qty 137.0 · bid tab
  • 2026-03-18 · KDOT · 526032131 · $105.15 per SQYD · qty 102.0 · bid tab
  • 2025-10-22 · KDOT · 525102181 · $108.00 per SQYD · qty 683.0 · bid tab
  • 2025-02-19 · KDOT · 525022161 · $186.55 per SQYD · qty 1211.0 · bid tab
  • 2025-02-19 · KDOT · 525022161 · $66.70 per SQYD · qty 25.0 · bid tab
  • 2025-02-19 · KDOT · 525022161 · $132.10 per SQYD · qty 877.0 · bid tab
  • 2025-02-19 · KDOT · 525026171 · $217.37 per SQYD · qty 92.0 · bid tab
  • 2025-02-19 · KDOT · 525026171 · $206.82 per SQYD · qty 52.0 · bid tab
  • 2024-11-20 · KDOT · 524112121 · $95.35 per SQYD · qty 23454.0 · bid tab
  • 2024-11-20 · KDOT · 524112121 · $207.98 per SQYD · qty 3470.0 · bid tab
(10 most recent of 22 shown; all in the Hubstake feed)
curb gutterLNFT16$60.95$24.00 to $275.00
Bids
  • 2026-03-18 · KDOT · 526032131 · $28.15 per LNFT · qty 1721.0 · bid tab
  • 2025-10-22 · KDOT · 525102181 · $32.00 per LNFT · qty 2537.0 · bid tab
  • 2025-02-19 · KDOT · 525022161 · $61.40 per LNFT · qty 117.0 · bid tab
  • 2025-02-19 · KDOT · 525026171 · $225.99 per LNFT · qty 20.0 · bid tab
  • 2025-02-19 · KDOT · 525026171 · $226.01 per LNFT · qty 70.0 · bid tab
  • 2025-02-19 · KDOT · 525026171 · $235.15 per LNFT · qty 12.0 · bid tab
  • 2024-11-20 · KDOT · 524112121 · $153.42 per LNFT · qty 17.0 · bid tab
  • 2024-11-20 · KDOT · 524116141 · $60.50 per LNFT · qty 2000.0 · bid tab
  • 2024-10-16 · KDOT · 524102241 · $48.00 per LNFT · qty 50.0 · bid tab
  • 2024-10-16 · KDOT · 524102241 · $68.00 per LNFT · qty 90.0 · bid tab
(10 most recent of 16 shown; all in the Hubstake feed)
excavation embankmentCUYD30$31.90$0.01 to $354.28
Bids
  • 2026-03-18 · KDOT · 526032131 · $44.35 per CUYD · qty 2300.0 · bid tab
  • 2026-03-18 · KDOT · 526032131 · $38.40 per CUYD · qty 16.0 · bid tab
  • 2025-10-22 · KDOT · 525102181 · $8.40 per CUYD · qty 2082.0 · bid tab
  • 2025-10-22 · KDOT · 525102181 · $150.00 per CUYD · qty 21.0 · bid tab
  • 2025-10-22 · KDOT · 525102181 · $29.00 per CUYD · qty 2509.0 · bid tab
  • 2025-04-16 · KDOT · 525046131 · $300.00 per CUYD · qty 570.0 · bid tab
  • 2025-04-16 · KDOT · 525046131 · $20.00 per CUYD · qty 489.0 · bid tab
  • 2025-04-16 · KDOT · 525046131 · $315.00 per CUYD · qty 306.0 · bid tab
  • 2025-02-19 · KDOT · 525022161 · $146.45 per CUYD · qty 114.0 · bid tab
  • 2025-02-19 · KDOT · 525022161 · $354.28 per CUYD · qty 9.0 · bid tab
(10 most recent of 30 shown; all in the Hubstake feed)
flexible baseMGAL9$40.00$40.00 to $40.00
Bids
  • 2026-03-18 · KDOT · 526032131 · $40.00 per MGAL · qty 1.0 · bid tab
  • 2025-10-22 · KDOT · 525102181 · $40.00 per MGAL · qty 1.0 · bid tab
  • 2024-11-20 · KDOT · 524112121 · $40.00 per MGAL · qty 1.0 · bid tab
  • 2024-10-16 · KDOT · 524102241 · $40.00 per MGAL · qty 1.0 · bid tab
  • 2024-10-16 · KDOT · 524102251 · $40.00 per MGAL · qty 1.0 · bid tab
  • 2024-06-20 · KDOT · 524062171 · $40.00 per MGAL · qty 1.0 · bid tab
  • 2024-02-21 · KDOT · 524022161 · $40.00 per MGAL · qty 1.0 · bid tab
  • 2023-11-15 · KDOT · 523112191 · $40.00 per MGAL · qty 1.0 · bid tab
  • 2023-11-15 · KDOT · 523112191 · $40.00 per MGAL · qty 1.0 · bid tab
flexible baseSQYD10$17.23$10.00 to $47.91
Bids
  • 2026-03-18 · KDOT · 526032131 · $16.95 per SQYD · qty 1730.0 · bid tab
  • 2025-10-22 · KDOT · 525102181 · $15.60 per SQYD · qty 2569.0 · bid tab
  • 2024-11-20 · KDOT · 524112121 · $17.52 per SQYD · qty 28246.0 · bid tab
  • 2024-10-16 · KDOT · 524102241 · $13.00 per SQYD · qty 943.0 · bid tab
  • 2024-10-16 · KDOT · 524102241 · $39.00 per SQYD · qty 55.0 · bid tab
  • 2024-10-16 · KDOT · 524102251 · $15.95 per SQYD · qty 596.0 · bid tab
  • 2024-06-20 · KDOT · 524062171 · $10.00 per SQYD · qty 15265.0 · bid tab
  • 2024-02-21 · KDOT · 524022161 · $47.91 per SQYD · qty 77.0 · bid tab
  • 2023-11-15 · KDOT · 523112191 · $17.94 per SQYD · qty 1792.0 · bid tab
  • 2023-11-15 · KDOT · 523112191 · $18.85 per SQYD · qty 511.0 · bid tab
inlet headwallCUYD1$88.71$88.71 to $88.71
Bids
  • 2023-11-15 · KDOT · 523112191 · $88.71 per CUYD · qty 52.0 · bid tab
inlet headwallEACH9$8,250.00$2,889.45 to $9,044.02
Bids
  • 2026-03-18 · KDOT · 526032131 · $8,309.75 per EACH · qty 5.0 · bid tab
  • 2025-10-22 · KDOT · 525102181 · $8,250.00 per EACH · qty 9.0 · bid tab
  • 2025-02-19 · KDOT · 525022161 · $8,507.30 per EACH · qty 1.0 · bid tab
  • 2024-06-20 · KDOT · 524062171 · $8,900.00 per EACH · qty 25.0 · bid tab
  • 2024-06-20 · KDOT · 524062171 · $6,300.00 per EACH · qty 1.0 · bid tab
  • 2024-06-20 · KDOT · 524062171 · $6,500.00 per EACH · qty 4.0 · bid tab
  • 2023-11-15 · KDOT · 523112191 · $9,044.02 per EACH · qty 2.0 · bid tab
  • 2023-11-15 · KDOT · 523112191 · $8,248.20 per EACH · qty 4.0 · bid tab
  • 2023-11-15 · KDOT · 523112191 · $2,889.45 per EACH · qty 1.0 · bid tab
lime cement stabilizationCUYD9$40.00$40.00 to $196.14
Bids
  • 2026-03-18 · KDOT · 526032131 · $40.00 per CUYD · qty 1.0 · bid tab
  • 2025-10-22 · KDOT · 525102181 · $40.00 per CUYD · qty 1.0 · bid tab
  • 2025-02-19 · KDOT · 525026151 · $196.14 per CUYD · qty 63.0 · bid tab
  • 2024-11-20 · KDOT · 524112121 · $40.00 per CUYD · qty 1.0 · bid tab
  • 2024-10-16 · KDOT · 524102251 · $40.00 per CUYD · qty 1.0 · bid tab
  • 2024-06-20 · KDOT · 524062171 · $40.00 per CUYD · qty 1.0 · bid tab
  • 2024-06-20 · KDOT · 524062171 · $70.00 per CUYD · qty 119.0 · bid tab
  • 2023-11-15 · KDOT · 523112191 · $40.00 per CUYD · qty 1.0 · bid tab
  • 2023-11-15 · KDOT · 523112191 · $173.43 per CUYD · qty 9.0 · bid tab
lime cement stabilizationEACH3$250.00$167.03 to $267.83
Bids
  • 2025-02-19 · KDOT · 525026171 · $267.83 per EACH · qty 15.0 · bid tab
  • 2024-09-18 · KDOT · 524096151 · $250.00 per EACH · qty 15.0 · bid tab
  • 2023-11-15 · KDOT · 523112191 · $167.03 per EACH · qty 15.0 · bid tab
lime cement stabilizationSQYD1$46.60$46.60 to $46.60
Bids
  • 2025-02-19 · KDOT · 525022161 · $46.60 per SQYD · qty 2088.0 · bid tab
manholeEACH5$7,652.77$5,625.46 to $16,500.00
Bids
  • 2025-10-22 · KDOT · 525102181 · $7,700.00 per EACH · qty 4.0 · bid tab
  • 2024-11-20 · KDOT · 524112121 · $6,566.44 per EACH · qty 46.0 · bid tab
  • 2024-11-20 · KDOT · 524112121 · $5,625.46 per EACH · qty 2.0 · bid tab
  • 2024-06-20 · KDOT · 524062171 · $16,500.00 per EACH · qty 1.0 · bid tab
  • 2023-11-15 · KDOT · 523112191 · $7,652.77 per EACH · qty 3.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.