Site-work prices, Woodson County, KS
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | TON | 1 | $134.46 | $134.46 to $134.46 | Bids
|
| concrete pavement | SQYD | 2 | $350.00 | $300.00 to $400.00 | |
| excavation embankment | CUYD | 7 | $13.44 | $1.00 to $35.00 | Bids
|
| flexible base | MGAL | 1 | $40.00 | $40.00 to $40.00 | Bids
|
| flexible base | SQYD | 1 | $9.20 | $9.20 to $9.20 | Bids
|
| inlet headwall | CUYD | 1 | $155.00 | $155.00 to $155.00 | Bids
|
| inlet headwall | EACH | 1 | $4,000.00 | $4,000.00 to $4,000.00 | Bids
|
| lime cement stabilization | CUYD | 3 | $40.00 | $40.00 to $150.00 | |
| lime cement stabilization | EACH | 3 | $5.00 | $0.10 to $200.00 |
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.