Site-work prices, Harper County, KS

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON7$96.00$1.00 to $1,352.00
Bids
  • 2026-08-19 · KDOT · 526086545 · $1,352.00 per TON · qty 327.0 · bid tab
  • 2025-10-22 · KDOT · 525102535 · $96.00 per TON · qty 9651.0 · bid tab
  • 2025-10-22 · KDOT · 525102535 · $1.00 per TON · qty 9651.0 · bid tab
  • 2024-10-16 · KDOT · 524102515 · $1.50 per TON · qty 13749.0 · bid tab
  • 2024-10-16 · KDOT · 524102515 · $78.00 per TON · qty 13749.0 · bid tab
  • 2024-10-16 · KDOT · 524102515 · $675.00 per TON · qty 36.0 · bid tab
  • 2024-03-20 · KDOT · 524032535 · $185.00 per TON · qty 482.0 · bid tab
concrete pavementSQYD4$126.50$72.00 to $210.00
Bids
  • 2025-06-18 · KDOT · 525062565 · $126.50 per SQYD · qty 1752.0 · bid tab
  • 2025-06-18 · KDOT · 525062565 · $126.50 per SQYD · qty 231.0 · bid tab
  • 2025-06-18 · KDOT · 525062565 · $72.00 per SQYD · qty 151.0 · bid tab
  • 2024-03-20 · KDOT · 524032535 · $210.00 per SQYD · qty 412.0 · bid tab
curb gutterLNFT1$48.60$48.60 to $48.60
Bids
  • 2025-06-18 · KDOT · 525062565 · $48.60 per LNFT · qty 496.0 · bid tab
excavation embankmentCUYD5$15.00$1.50 to $37.35
Bids
  • 2025-06-18 · KDOT · 525062565 · $37.35 per CUYD · qty 472.0 · bid tab
  • 2024-03-20 · KDOT · 524032535 · $15.00 per CUYD · qty 1241.0 · bid tab
  • 2024-03-20 · KDOT · 524032535 · $20.00 per CUYD · qty 3125.0 · bid tab
  • 2024-03-20 · KDOT · 524032535 · $1.50 per CUYD · qty 2893.0 · bid tab
  • 2024-03-20 · KDOT · 524032535 · $2.00 per CUYD · qty 553.0 · bid tab
flexible baseMGAL2$26.00$12.00 to $40.00
Bids
  • 2025-06-18 · KDOT · 525062565 · $12.00 per MGAL · qty 1.0 · bid tab
  • 2024-03-20 · KDOT · 524032535 · $40.00 per MGAL · qty 1.0 · bid tab
flexible baseSQYD2$18.93$17.85 to $20.00
Bids
  • 2025-06-18 · KDOT · 525062565 · $17.85 per SQYD · qty 2121.0 · bid tab
  • 2024-03-20 · KDOT · 524032535 · $20.00 per SQYD · qty 1539.0 · bid tab
inlet headwallEACH1$2,500.00$2,500.00 to $2,500.00
Bids
  • 2024-03-20 · KDOT · 524032535 · $2,500.00 per EACH · qty 4.0 · bid tab
lime cement stabilizationCUYD1$40.00$40.00 to $40.00
Bids
  • 2024-03-20 · KDOT · 524032535 · $40.00 per CUYD · qty 1.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.