Site-work prices, Dickinson County, KS

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON11$121.00$2.00 to $900.00
Bids
  • 2026-10-21 · KDOT · 526106212 · $900.00 per TON · qty 166.0 · bid tab
  • 2026-01-21 · KDOT · 526012232 · $121.00 per TON · qty 1994.0 · bid tab
  • 2025-12-17 · KDOT · 525122242 · $77.50 per TON · qty 36258.0 · bid tab
  • 2025-12-17 · KDOT · 525122242 · $2.00 per TON · qty 85737.0 · bid tab
  • 2025-12-17 · KDOT · 525122242 · $195.00 per TON · qty 12370.0 · bid tab
  • 2025-12-17 · KDOT · 525122242 · $722.00 per TON · qty 165.6 · bid tab
  • 2025-12-17 · KDOT · 525122242 · $87.00 per TON · qty 37109.0 · bid tab
  • 2025-03-19 · KDOT · 525032232 · $134.00 per TON · qty 871.0 · bid tab
  • 2024-12-18 · KDOT · 524126212 · $2.20 per TON · qty 26611.0 · bid tab
  • 2024-12-18 · KDOT · 524126212 · $79.00 per TON · qty 26611.0 · bid tab
(10 most recent of 11 shown; all in the Hubstake feed)
concrete pavementSQYD4$408.06$210.00 to $2,200.00
Bids
  • 2026-10-21 · KDOT · 526106242 · $541.12 per SQYD · qty 80.0 · bid tab
  • 2026-01-21 · KDOT · 526012232 · $275.00 per SQYD · qty 418.0 · bid tab
  • 2025-10-22 · KDOT · 525106232 · $2,200.00 per SQYD · qty 8.0 · bid tab
  • 2025-03-19 · KDOT · 525032232 · $210.00 per SQYD · qty 81.0 · bid tab
excavation embankmentCUYD7$8.00$1.45 to $41.00
Bids
  • 2026-01-21 · KDOT · 526012232 · $5.00 per CUYD · qty 238.0 · bid tab
  • 2026-01-21 · KDOT · 526012232 · $11.35 per CUYD · qty 19596.0 · bid tab
  • 2026-01-21 · KDOT · 526012232 · $8.00 per CUYD · qty 1998.0 · bid tab
  • 2026-01-21 · KDOT · 526012232 · $1.45 per CUYD · qty 16575.0 · bid tab
  • 2025-03-19 · KDOT · 525032232 · $2.25 per CUYD · qty 562.0 · bid tab
  • 2025-03-19 · KDOT · 525032232 · $8.00 per CUYD · qty 2247.0 · bid tab
  • 2024-12-18 · KDOT · 524126212 · $41.00 per CUYD · qty 823.0 · bid tab
flexible baseMGAL2$40.00$40.00 to $40.00
Bids
  • 2026-01-21 · KDOT · 526012232 · $40.00 per MGAL · qty 1.0 · bid tab
  • 2025-03-19 · KDOT · 525032232 · $40.00 per MGAL · qty 1.0 · bid tab
flexible baseSQYD3$10.12$7.25 to $15.00
Bids
  • 2026-01-21 · KDOT · 526012232 · $10.12 per SQYD · qty 3954.0 · bid tab
  • 2025-03-19 · KDOT · 525032232 · $15.00 per SQYD · qty 1505.0 · bid tab
  • 2024-12-18 · KDOT · 524126212 · $7.25 per SQYD · qty 4233.0 · bid tab
inlet headwallEACH1$4,250.00$4,250.00 to $4,250.00
Bids
  • 2026-01-21 · KDOT · 526012232 · $4,250.00 per EACH · qty 4.0 · bid tab
lime cement stabilizationCUYD2$40.00$40.00 to $40.00
Bids
  • 2026-01-21 · KDOT · 526012232 · $40.00 per CUYD · qty 1.0 · bid tab
  • 2025-03-19 · KDOT · 525032232 · $40.00 per CUYD · qty 1.0 · bid tab
lime cement stabilizationEACH1$25.00$25.00 to $25.00
Bids
  • 2025-10-22 · KDOT · 525106232 · $25.00 per EACH · qty 10.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.