| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 37 | $125.00 | $65.00 to $350.00 | Bids- 2025-12-10 · INDOT · B-43610-A · $350.00 per TON · qty 5.0 · bid tab
- 2025-12-10 · INDOT · B-43610-A · $125.00 per TON · qty 285.0 · bid tab
- 2025-12-10 · INDOT · B-43610-A · $220.00 per TON · qty 171.0 · bid tab
- 2025-12-10 · INDOT · B-43610-A · $90.00 per TON · qty 697.0 · bid tab
- 2025-08-06 · INDOT · B-42780-A · $225.00 per TON · qty 13.0 · bid tab
- 2025-08-06 · INDOT · B-42780-A · $90.00 per TON · qty 60.0 · bid tab
- 2025-08-06 · INDOT · B-42780-A · $65.00 per TON · qty 165.0 · bid tab
- 2025-08-06 · INDOT · B-42780-A · $110.00 per TON · qty 45.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $113.00 per TON · qty 568.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $102.00 per TON · qty 2371.0 · bid tab
(10 most recent of 37 shown; all in the Hubstake feed) |
| curb gutter | EACH | 6 | $3,025.00 | $2,550.00 to $3,970.00 | Bids- 2025-12-10 · INDOT · B-43610-A · $3,325.00 per EACH · qty 4.0 · bid tab
- 2025-08-06 · INDOT · B-42780-A · $2,850.00 per EACH · qty 1.0 · bid tab
- 2025-08-06 · INDOT · B-42780-A · $2,850.00 per EACH · qty 2.0 · bid tab
- 2024-11-14 · INDOT · B-41854-A · $2,550.00 per EACH · qty 4.0 · bid tab
- 2024-09-11 · INDOT · B-41551-A · $3,200.00 per EACH · qty 5.0 · bid tab
- 2023-12-13 · INDOT · B-42779-A · $3,970.00 per EACH · qty 4.0 · bid tab
|
| curb gutter | LFT | 6 | $57.05 | $29.00 to $93.00 | Bids- 2025-08-06 · INDOT · B-42780-A · $93.00 per LFT · qty 171.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $55.00 per LFT · qty 235.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $80.00 per LFT · qty 30.0 · bid tab
- 2024-11-14 · INDOT · B-41854-A · $52.50 per LFT · qty 25.0 · bid tab
- 2024-11-14 · INDOT · B-41854-A · $29.00 per LFT · qty 1447.0 · bid tab
- 2024-09-11 · INDOT · B-41551-A · $59.10 per LFT · qty 429.0 · bid tab
|
| curb gutter | SYS | 1 | $90.00 | $90.00 to $90.00 | Bids- 2025-07-09 · INDOT · R-43285-A · $90.00 per SYS · qty 177.0 · bid tab
|
| excavation embankment | LS | 8 | $221,925.00 | $75,000.00 to $549,593.30 | Bids- 2025-12-10 · INDOT · B-43610-A · $129,274.48 per LS · qty 1.0 · bid tab
- 2025-08-06 · INDOT · B-42780-A · $184,000.00 per LS · qty 1.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $540,000.00 per LS · qty 1.0 · bid tab
- 2025-01-15 · INDOT · R-44290-A · $149,000.00 per LS · qty 1.0 · bid tab
- 2024-11-14 · INDOT · B-41854-A · $259,850.00 per LS · qty 1.0 · bid tab
- 2024-09-11 · INDOT · B-41551-A · $549,593.30 per LS · qty 1.0 · bid tab
- 2023-12-13 · INDOT · B-42366-A · $381,893.19 per LS · qty 1.0 · bid tab
- 2023-12-13 · INDOT · B-42779-A · $75,000.00 per LS · qty 1.0 · bid tab
|
| fire hydrant | EACH | 1 | $12,700.00 | $12,700.00 to $12,700.00 | Bids- 2024-09-11 · INDOT · B-41551-A · $12,700.00 per EACH · qty 2.0 · bid tab
|
| inlet headwall | EACH | 16 | $4,150.00 | $933.93 to $7,200.00 | Bids- 2025-08-06 · INDOT · B-42780-A · $4,000.00 per EACH · qty 1.0 · bid tab
- 2025-08-06 · INDOT · B-42780-A · $4,000.00 per EACH · qty 1.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $4,900.00 per EACH · qty 5.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $4,100.00 per EACH · qty 2.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $6,500.00 per EACH · qty 3.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $7,200.00 per EACH · qty 4.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $3,400.00 per EACH · qty 1.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $5,400.00 per EACH · qty 1.0 · bid tab
- 2024-11-14 · INDOT · B-41854-A · $2,073.48 per EACH · qty 4.0 · bid tab
- 2024-11-14 · INDOT · B-41854-A · $933.93 per EACH · qty 1.0 · bid tab
(10 most recent of 16 shown; all in the Hubstake feed) |
| inlet headwall | LFT | 1 | $1,775.00 | $1,775.00 to $1,775.00 | Bids- 2024-09-11 · INDOT · B-41551-A · $1,775.00 per LFT · qty 6.0 · bid tab
|
| lime cement stabilization | SYS | 14 | $27.69 | $4.12 to $55.00 | Bids- 2025-12-10 · INDOT · B-43610-A · $25.98 per SYS · qty 2591.0 · bid tab
- 2025-12-10 · INDOT · B-43610-A · $15.65 per SYS · qty 54.0 · bid tab
- 2025-12-10 · INDOT · B-43610-A · $12.00 per SYS · qty 1385.0 · bid tab
- 2025-08-06 · INDOT · B-42780-A · $30.00 per SYS · qty 78.0 · bid tab
- 2025-08-06 · INDOT · B-42780-A · $52.00 per SYS · qty 695.0 · bid tab
- 2025-07-09 · INDOT · R-43285-A · $37.00 per SYS · qty 18258.0 · bid tab
- 2025-01-15 · INDOT · R-44290-A · $4.12 per SYS · qty 1807.0 · bid tab
- 2024-11-14 · INDOT · B-41854-A · $26.94 per SYS · qty 106.0 · bid tab
- 2024-11-14 · INDOT · B-41854-A · $25.00 per SYS · qty 2533.0 · bid tab
- 2024-11-14 · INDOT · B-41854-A · $28.43 per SYS · qty 419.0 · bid tab
(10 most recent of 14 shown; all in the Hubstake feed) |
| manhole | EACH | 5 | $4,310.37 | $3,575.94 to $11,000.00 | Bids- 2025-07-09 · INDOT · R-43285-A · $4,300.00 per EACH · qty 1.0 · bid tab
- 2024-11-14 · INDOT · B-41854-A · $4,310.37 per EACH · qty 3.0 · bid tab
- 2024-11-14 · INDOT · B-41854-A · $4,682.99 per EACH · qty 1.0 · bid tab
- 2024-09-11 · INDOT · B-41551-A · $11,000.00 per EACH · qty 3.0 · bid tab
- 2023-12-13 · INDOT · B-42366-A · $3,575.94 per EACH · qty 2.0 · bid tab
|
| sewer service | EACH | 1 | $1,500.00 | $1,500.00 to $1,500.00 | Bids- 2024-09-11 · INDOT · B-41551-A · $1,500.00 per EACH · qty 2.0 · bid tab
|
| sewer service | LFT | 1 | $138.00 | $138.00 to $138.00 | Bids- 2024-09-11 · INDOT · B-41551-A · $138.00 per LFT · qty 40.0 · bid tab
|
| water service | EACH | 1 | $530.00 | $530.00 to $530.00 | Bids- 2024-09-11 · INDOT · B-41551-A · $530.00 per EACH · qty 3.0 · bid tab
|