Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | TON | 9 | $115.00 | $100.00 to $220.00 | Bids
|
| curb gutter | EACH | 1 | $3,378.70 | $3,378.70 to $3,378.70 | Bids
|
| curb gutter | LFT | 2 | $207.50 | $65.00 to $350.00 | |
| curb gutter | SYS | 1 | $140.00 | $140.00 to $140.00 | Bids
|
| excavation embankment | LS | 1 | $379,815.00 | $379,815.00 to $379,815.00 | Bids
|
| inlet headwall | EACH | 4 | $5,450.00 | $4,500.00 to $9,500.00 | |
| lime cement stabilization | SYS | 1 | $43.00 | $43.00 to $43.00 | Bids
|
| manhole | EACH | 1 | $4,000.00 | $4,000.00 to $4,000.00 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.