Site-work prices, Noble County, IN

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON51$125.00$70.00 to $500.00
Bids
  • 2026-09-02 · INDOT · B-45066-A · $235.00 per TON · qty 177.0 · bid tab
  • 2026-09-02 · INDOT · B-45066-A · $125.00 per TON · qty 674.0 · bid tab
  • 2026-09-02 · INDOT · B-45066-A · $155.00 per TON · qty 210.0 · bid tab
  • 2026-07-08 · INDOT · B-44339-A · $205.00 per TON · qty 75.0 · bid tab
  • 2026-07-08 · INDOT · B-44339-A · $245.00 per TON · qty 45.0 · bid tab
  • 2026-03-11 · INDOT · B-42777-A · $115.00 per TON · qty 295.0 · bid tab
  • 2026-03-11 · INDOT · B-42777-A · $86.00 per TON · qty 830.0 · bid tab
  • 2026-03-11 · INDOT · B-42777-A · $115.00 per TON · qty 194.0 · bid tab
  • 2026-03-11 · INDOT · B-42777-A · $95.00 per TON · qty 505.0 · bid tab
  • 2026-02-11 · INDOT · B-42775-A · $210.00 per TON · qty 21.0 · bid tab
(10 most recent of 51 shown; all in the Hubstake feed)
curb gutterEACH6$3,262.50$3,000.00 to $3,700.00
Bids
  • 2026-09-02 · INDOT · B-45066-A · $3,000.00 per EACH · qty 4.0 · bid tab
  • 2026-03-11 · INDOT · B-42777-A · $3,425.00 per EACH · qty 4.0 · bid tab
  • 2026-02-11 · INDOT · B-42775-A · $3,045.00 per EACH · qty 2.0 · bid tab
  • 2025-07-09 · INDOT · R-43310-A · $3,700.00 per EACH · qty 2.0 · bid tab
  • 2024-04-10 · INDOT · B-42376-A · $3,100.00 per EACH · qty 3.0 · bid tab
  • 2024-04-10 · INDOT · B-42376-A · $3,450.00 per EACH · qty 1.0 · bid tab
curb gutterLFT14$97.50$4.11 to $267.33
Bids
  • 2026-02-11 · INDOT · B-42775-A · $103.00 per LFT · qty 20.0 · bid tab
  • 2026-02-11 · INDOT · B-42775-A · $130.00 per LFT · qty 5.0 · bid tab
  • 2025-07-09 · INDOT · R-43185-A · $267.33 per LFT · qty 12.0 · bid tab
  • 2025-07-09 · INDOT · R-43185-A · $47.57 per LFT · qty 210.0 · bid tab
  • 2025-07-09 · INDOT · R-43185-A · $4.11 per LFT · qty 24.0 · bid tab
  • 2025-07-09 · INDOT · R-43310-A · $110.00 per LFT · qty 63.0 · bid tab
  • 2025-07-09 · INDOT · R-43310-A · $95.00 per LFT · qty 129.0 · bid tab
  • 2025-07-09 · INDOT · R-43310-A · $95.00 per LFT · qty 96.0 · bid tab
  • 2024-12-11 · INDOT · R-42771-A · $28.00 per LFT · qty 7277.0 · bid tab
  • 2024-12-11 · INDOT · R-42771-A · $70.00 per LFT · qty 149.0 · bid tab
(10 most recent of 14 shown; all in the Hubstake feed)
excavation embankmentLS13$74,000.00$33,000.00 to $482,000.00
Bids
  • 2026-09-02 · INDOT · B-45066-A · $95,800.00 per LS · qty 1.0 · bid tab
  • 2026-07-08 · INDOT · B-44339-A · $59,384.76 per LS · qty 1.0 · bid tab
  • 2026-03-11 · INDOT · B-42777-A · $182,600.00 per LS · qty 1.0 · bid tab
  • 2026-02-11 · INDOT · B-42775-A · $69,392.76 per LS · qty 1.0 · bid tab
  • 2025-07-09 · INDOT · R-43185-A · $97,650.00 per LS · qty 1.0 · bid tab
  • 2025-07-09 · INDOT · R-43310-A · $309,822.00 per LS · qty 1.0 · bid tab
  • 2025-07-09 · INDOT · R-43612-A · $55,000.00 per LS · qty 1.0 · bid tab
  • 2024-12-11 · INDOT · R-42771-A · $255,000.00 per LS · qty 1.0 · bid tab
  • 2024-12-11 · INDOT · R-42776-A · $33,000.00 per LS · qty 1.0 · bid tab
  • 2024-12-11 · INDOT · R-43303-B · $482,000.00 per LS · qty 1.0 · bid tab
(10 most recent of 13 shown; all in the Hubstake feed)
inlet headwallEACH10$3,742.18$3,000.00 to $6,500.00
Bids
  • 2026-03-11 · INDOT · B-42777-A · $3,000.00 per EACH · qty 1.0 · bid tab
  • 2026-03-11 · INDOT · B-42777-A · $3,200.00 per EACH · qty 3.0 · bid tab
  • 2025-07-09 · INDOT · R-43185-A · $4,199.36 per EACH · qty 17.0 · bid tab
  • 2025-07-09 · INDOT · R-43185-A · $4,084.37 per EACH · qty 1.0 · bid tab
  • 2024-12-11 · INDOT · R-42771-A · $3,400.00 per EACH · qty 15.0 · bid tab
  • 2024-12-11 · INDOT · R-42771-A · $3,000.00 per EACH · qty 1.0 · bid tab
  • 2024-12-11 · INDOT · R-42771-A · $3,400.00 per EACH · qty 12.0 · bid tab
  • 2024-12-11 · INDOT · R-43303-B · $5,250.00 per EACH · qty 2.0 · bid tab
  • 2024-01-18 · INDOT · R-42389-A · $6,500.00 per EACH · qty 1.0 · bid tab
  • 2024-01-18 · INDOT · R-42389-A · $6,500.00 per EACH · qty 2.0 · bid tab
lime cement stabilizationSYS21$33.00$3.00 to $60.00
Bids
  • 2026-09-02 · INDOT · B-45066-A · $46.00 per SYS · qty 1529.0 · bid tab
  • 2026-07-08 · INDOT · B-44339-A · $36.00 per SYS · qty 580.0 · bid tab
  • 2026-03-11 · INDOT · B-42777-A · $4.00 per SYS · qty 4075.0 · bid tab
  • 2026-03-11 · INDOT · B-42777-A · $29.00 per SYS · qty 485.0 · bid tab
  • 2026-02-11 · INDOT · B-42775-A · $38.00 per SYS · qty 1519.0 · bid tab
  • 2026-02-11 · INDOT · B-42775-A · $21.00 per SYS · qty 210.0 · bid tab
  • 2025-07-09 · INDOT · R-43185-A · $3.00 per SYS · qty 906.0 · bid tab
  • 2025-07-09 · INDOT · R-43185-A · $38.00 per SYS · qty 4449.0 · bid tab
  • 2025-07-09 · INDOT · R-43310-A · $31.50 per SYS · qty 153.0 · bid tab
  • 2025-07-09 · INDOT · R-43310-A · $50.00 per SYS · qty 3761.0 · bid tab
(10 most recent of 21 shown; all in the Hubstake feed)
manholeEACH7$5,900.00$4,200.00 to $11,000.00
Bids
  • 2024-12-11 · INDOT · R-42771-A · $6,200.00 per EACH · qty 1.0 · bid tab
  • 2024-12-11 · INDOT · R-42771-A · $5,900.00 per EACH · qty 5.0 · bid tab
  • 2024-12-11 · INDOT · R-42771-A · $4,250.00 per EACH · qty 2.0 · bid tab
  • 2024-12-11 · INDOT · R-42771-A · $4,200.00 per EACH · qty 4.0 · bid tab
  • 2024-12-11 · INDOT · R-42771-A · $11,000.00 per EACH · qty 1.0 · bid tab
  • 2024-12-11 · INDOT · R-42771-A · $6,200.00 per EACH · qty 3.0 · bid tab
  • 2024-12-11 · INDOT · R-43303-B · $5,850.00 per EACH · qty 2.0 · bid tab
sidewalkEACH2$4,240.50$2,981.00 to $5,500.00
Bids
  • 2026-09-02 · INDOT · B-45066-A · $5,500.00 per EACH · qty 2.0 · bid tab
  • 2025-07-09 · INDOT · R-43310-A · $2,981.00 per EACH · qty 3.0 · bid tab
water serviceEACH1$600.00$600.00 to $600.00
Bids
  • 2024-12-11 · INDOT · R-42771-A · $600.00 per EACH · qty 9.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.