| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 38 | $193.50 | $100.00 to $600.00 | Bids- 2026-05-07 · INDOT · R-43927-A · $190.00 per TON · qty 32.0 · bid tab
- 2026-05-07 · INDOT · R-43927-A · $320.00 per TON · qty 14.0 · bid tab
- 2026-05-07 · INDOT · R-43927-A · $130.50 per TON · qty 129.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $180.00 per TON · qty 132.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $150.00 per TON · qty 569.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $135.00 per TON · qty 715.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $160.00 per TON · qty 166.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $100.00 per TON · qty 2277.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $240.00 per TON · qty 42.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $310.00 per TON · qty 44.0 · bid tab
(10 most recent of 38 shown; all in the Hubstake feed) |
| concrete pavement | SYS | 1 | $180.00 | $180.00 to $180.00 | Bids- 2025-12-10 · INDOT · B-43917-A · $180.00 per SYS · qty 742.0 · bid tab
|
| curb gutter | EACH | 5 | $3,575.00 | $3,104.00 to $3,995.00 | Bids- 2025-12-10 · INDOT · B-43917-A · $3,550.00 per EACH · qty 4.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $3,600.00 per EACH · qty 8.0 · bid tab
- 2025-07-09 · INDOT · B-43926-A · $3,575.00 per EACH · qty 3.0 · bid tab
- 2025-02-12 · INDOT · B-43363-A · $3,104.00 per EACH · qty 4.0 · bid tab
- 2024-03-13 · INDOT · B-41427-A · $3,995.00 per EACH · qty 1.0 · bid tab
|
| curb gutter | LFT | 5 | $100.00 | $50.00 to $220.00 | Bids- 2025-12-10 · INDOT · B-43917-A · $100.00 per LFT · qty 28.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $50.00 per LFT · qty 199.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $58.00 per LFT · qty 166.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $220.00 per LFT · qty 10.0 · bid tab
- 2025-07-09 · INDOT · B-43926-A · $100.00 per LFT · qty 135.0 · bid tab
|
| excavation embankment | LS | 14 | $58,690.79 | $16,580.00 to $735,000.00 | Bids- 2026-05-07 · INDOT · R-43927-A · $51,350.00 per LS · qty 1.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $483,000.00 per LS · qty 1.0 · bid tab
- 2025-07-09 · INDOT · B-43926-A · $62,500.00 per LS · qty 1.0 · bid tab
- 2025-07-09 · INDOT · B-45854-A · $16,580.00 per LS · qty 1.0 · bid tab
- 2025-07-09 · INDOT · R-43878-A · $24,000.00 per LS · qty 1.0 · bid tab
- 2025-02-12 · INDOT · B-43363-A · $37,500.00 per LS · qty 1.0 · bid tab
- 2024-10-09 · INDOT · B-42828-A · $56,481.57 per LS · qty 1.0 · bid tab
- 2024-10-09 · INDOT · R-45225-A · $735,000.00 per LS · qty 1.0 · bid tab
- 2024-09-11 · INDOT · B-43339-A · $93,615.33 per LS · qty 1.0 · bid tab
- 2024-03-20 · INDOT · R-45457-A · $700,000.00 per LS · qty 1.0 · bid tab
(10 most recent of 14 shown; all in the Hubstake feed) |
| inlet headwall | EACH | 3 | $2,600.00 | $1,120.00 to $2,600.00 | Bids- 2025-12-10 · INDOT · B-43917-A · $2,600.00 per EACH · qty 2.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $2,600.00 per EACH · qty 8.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $1,120.00 per EACH · qty 7.0 · bid tab
|
| lime cement stabilization | SYS | 11 | $52.00 | $15.00 to $100.00 | Bids- 2026-05-07 · INDOT · R-43927-A · $33.50 per SYS · qty 104.0 · bid tab
- 2025-12-10 · INDOT · B-43917-A · $15.00 per SYS · qty 17297.0 · bid tab
- 2025-07-09 · INDOT · B-43926-A · $95.00 per SYS · qty 278.0 · bid tab
- 2025-07-09 · INDOT · B-43926-A · $55.00 per SYS · qty 262.0 · bid tab
- 2025-07-09 · INDOT · R-43878-A · $52.00 per SYS · qty 129.0 · bid tab
- 2025-02-12 · INDOT · B-43363-A · $51.00 per SYS · qty 498.0 · bid tab
- 2024-03-13 · INDOT · B-41427-A · $47.00 per SYS · qty 1082.0 · bid tab
- 2024-03-13 · INDOT · B-41427-A · $33.03 per SYS · qty 35.0 · bid tab
- 2023-12-13 · INDOT · B-43139-A · $65.00 per SYS · qty 104.0 · bid tab
- 2023-12-13 · INDOT · B-43139-A · $100.00 per SYS · qty 108.0 · bid tab
(10 most recent of 11 shown; all in the Hubstake feed) |
| manhole | EACH | 1 | $4,400.00 | $4,400.00 to $4,400.00 | Bids- 2025-12-10 · INDOT · B-43917-A · $4,400.00 per EACH · qty 2.0 · bid tab
|