| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 45 | $130.00 | $73.50 to $1,400.00 | Bids- 2026-07-08 · INDOT · B-44244-A · $193.00 per TON · qty 30.0 · bid tab
- 2026-07-08 · INDOT · B-44244-A · $123.00 per TON · qty 231.0 · bid tab
- 2026-07-08 · INDOT · B-44244-A · $127.00 per TON · qty 151.0 · bid tab
- 2026-07-08 · INDOT · B-44244-A · $142.00 per TON · qty 113.0 · bid tab
- 2026-03-11 · INDOT · B-44998-A · $117.39 per TON · qty 236.0 · bid tab
- 2026-03-11 · INDOT · B-44998-A · $106.57 per TON · qty 751.0 · bid tab
- 2026-03-11 · INDOT · B-44998-A · $152.41 per TON · qty 142.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $98.00 per TON · qty 670.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $82.00 per TON · qty 786.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $133.00 per TON · qty 405.0 · bid tab
(10 most recent of 45 shown; all in the Hubstake feed) |
| curb gutter | EACH | 5 | $3,050.00 | $2,900.00 to $3,200.00 | Bids- 2026-03-11 · INDOT · B-44998-A · $3,055.00 per EACH · qty 4.0 · bid tab
- 2025-02-12 · INDOT · B-43418-A · $2,900.00 per EACH · qty 3.0 · bid tab
- 2024-12-11 · INDOT · R-44240-A · $2,950.00 per EACH · qty 3.0 · bid tab
- 2024-12-11 · INDOT · R-44240-A · $3,050.00 per EACH · qty 2.0 · bid tab
- 2024-11-14 · INDOT · B-44938-A · $3,200.00 per EACH · qty 4.0 · bid tab
|
| curb gutter | LFT | 18 | $38.75 | $26.00 to $200.00 | Bids- 2026-07-08 · INDOT · B-44244-A · $55.00 per LFT · qty 216.0 · bid tab
- 2026-07-08 · INDOT · B-44244-A · $45.00 per LFT · qty 69.0 · bid tab
- 2026-03-11 · INDOT · B-44998-A · $142.03 per LFT · qty 10.0 · bid tab
- 2026-03-11 · INDOT · B-44998-A · $31.41 per LFT · qty 1096.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $28.00 per LFT · qty 2250.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $28.00 per LFT · qty 972.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $26.00 per LFT · qty 378.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $55.00 per LFT · qty 123.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $28.00 per LFT · qty 3183.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $40.00 per LFT · qty 289.0 · bid tab
(10 most recent of 18 shown; all in the Hubstake feed) |
| curb gutter | SYS | 2 | $234.00 | $155.00 to $313.00 | Bids- 2026-02-11 · INDOT · R-43599-A · $313.00 per SYS · qty 15.0 · bid tab
- 2024-12-11 · INDOT · R-44240-A · $155.00 per SYS · qty 1005.0 · bid tab
|
| excavation embankment | LS | 17 | $87,500.00 | $13,255.00 to $3,000,000.00 | Bids- 2026-08-05 · INDOT · B-43555-A · $15,469.50 per LS · qty 1.0 · bid tab
- 2026-07-08 · INDOT · B-44244-A · $87,500.00 per LS · qty 1.0 · bid tab
- 2026-03-11 · INDOT · B-44998-A · $208,684.97 per LS · qty 1.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $119,156.53 per LS · qty 1.0 · bid tab
- 2025-12-10 · INDOT · B-45490-A · $40,000.00 per LS · qty 1.0 · bid tab
- 2025-09-10 · INDOT · T-44858-A · $35,000.00 per LS · qty 1.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $496,180.24 per LS · qty 1.0 · bid tab
- 2025-02-12 · INDOT · B-43418-A · $45,000.00 per LS · qty 1.0 · bid tab
- 2024-12-11 · INDOT · R-44240-A · $3,000,000.00 per LS · qty 1.0 · bid tab
- 2024-11-14 · INDOT · B-43437-A · $120,000.00 per LS · qty 1.0 · bid tab
(10 most recent of 17 shown; all in the Hubstake feed) |
| fire hydrant | EACH | 1 | $10,500.00 | $10,500.00 to $10,500.00 | Bids- 2025-07-09 · INDOT · R-44250-A · $10,500.00 per EACH · qty 2.0 · bid tab
|
| inlet headwall | EACH | 10 | $3,200.00 | $2,900.00 to $4,500.00 | Bids- 2026-03-11 · INDOT · B-44998-A · $4,159.38 per EACH · qty 3.0 · bid tab
- 2026-03-11 · INDOT · B-44998-A · $4,129.50 per EACH · qty 4.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $3,100.00 per EACH · qty 7.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $3,100.00 per EACH · qty 3.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $3,000.00 per EACH · qty 3.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $2,900.00 per EACH · qty 10.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $2,900.00 per EACH · qty 31.0 · bid tab
- 2024-12-11 · INDOT · R-44240-A · $3,300.00 per EACH · qty 44.0 · bid tab
- 2024-12-11 · INDOT · R-44240-A · $3,400.00 per EACH · qty 12.0 · bid tab
- 2024-12-11 · INDOT · R-44240-A · $4,500.00 per EACH · qty 16.0 · bid tab
|
| lime cement stabilization | SYS | 21 | $27.00 | $1.00 to $100.00 | Bids- 2026-07-08 · INDOT · B-44244-A · $25.00 per SYS · qty 151.0 · bid tab
- 2026-07-08 · INDOT · B-44244-A · $45.00 per SYS · qty 1578.0 · bid tab
- 2026-03-11 · INDOT · B-44998-A · $42.28 per SYS · qty 2262.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $6.00 per SYS · qty 902.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $27.00 per SYS · qty 6608.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $25.00 per SYS · qty 461.0 · bid tab
- 2025-12-10 · INDOT · B-45490-A · $45.00 per SYS · qty 1362.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $16.00 per SYS · qty 7866.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $28.00 per SYS · qty 1232.0 · bid tab
- 2024-12-11 · INDOT · R-44240-A · $1.00 per SYS · qty 12941.0 · bid tab
(10 most recent of 21 shown; all in the Hubstake feed) |
| manhole | EACH | 22 | $5,393.14 | $2,800.00 to $18,000.00 | Bids- 2026-03-11 · INDOT · B-44998-A · $6,589.15 per EACH · qty 2.0 · bid tab
- 2026-03-11 · INDOT · B-44998-A · $5,236.27 per EACH · qty 1.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $4,670.00 per EACH · qty 4.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $18,000.00 per EACH · qty 1.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $4,610.00 per EACH · qty 2.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $5,550.00 per EACH · qty 1.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $6,990.00 per EACH · qty 1.0 · bid tab
- 2026-02-11 · INDOT · R-43599-A · $6,550.00 per EACH · qty 1.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $3,500.00 per EACH · qty 8.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $2,800.00 per EACH · qty 7.0 · bid tab
(10 most recent of 22 shown; all in the Hubstake feed) |
| water service | EACH | 1 | $1,465.00 | $1,465.00 to $1,465.00 | Bids- 2025-07-09 · INDOT · R-44250-A · $1,465.00 per EACH · qty 11.0 · bid tab
|
| water service | LFT | 2 | $132.50 | $70.00 to $195.00 | Bids- 2025-07-09 · INDOT · R-44250-A · $195.00 per LFT · qty 49.0 · bid tab
- 2025-07-09 · INDOT · R-44250-A · $70.00 per LFT · qty 120.0 · bid tab
|