Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementSQ YD88$20.47$0.01 to $166.78
Bids
  • 2026-07-31 · IDOT · Section 2RS-6,PP · $98.95 per SQ YD · qty 98.0 · bid tab
  • 2026-07-31 · IDOT · Section 2RS-6,PP · $90.62 per SQ YD · qty 86.0 · bid tab
  • 2026-07-31 · IDOT · Section 2RS-6,PP · $15.08 per SQ YD · qty 5819.0 · bid tab
  • 2026-07-31 · IDOT · Section 2RS-6,PP · $32.38 per SQ YD · qty 314.0 · bid tab
  • 2026-06-12 · IDOT · Section (10R)RS-8 · $7.87 per SQ YD · qty 31482.0 · bid tab
  • 2026-06-12 · IDOT · Section (10R)RS-8 · $44.43 per SQ YD · qty 1041.0 · bid tab
  • 2026-06-12 · IDOT · Section (10R)RS-8 · $59.17 per SQ YD · qty 996.0 · bid tab
  • 2026-06-12 · IDOT · Section 72[6RS;(6-1)RS-1] · $7.45 per SQ YD · qty 52685.0 · bid tab
  • 2026-06-12 · IDOT · Section 72[6RS;(6-1)RS-1] · $33.50 per SQ YD · qty 1158.1 · bid tab
  • 2026-06-12 · IDOT · Section 72[6RS;(6-1)RS-1] · $5.00 per SQ YD · qty 1577.0 · bid tab
(10 most recent of 88 shown; all in the Hubstake feed)
asphalt pavementTON74$203.27$95.00 to $627.65
Bids
  • 2026-07-31 · IDOT · Section 2RS-6,PP · $557.10 per TON · qty 9.0 · bid tab
  • 2026-07-31 · IDOT · Section 2RS-6,PP · $293.65 per TON · qty 601.0 · bid tab
  • 2026-07-31 · IDOT · Section 2RS-6,PP · $332.68 per TON · qty 342.0 · bid tab
  • 2026-06-12 · IDOT · Section (10R)RS-8 · $204.99 per TON · qty 3087.0 · bid tab
  • 2026-06-12 · IDOT · Section (10R)RS-8 · $627.65 per TON · qty 196.0 · bid tab
  • 2026-06-12 · IDOT · Section (10R)RS-8 · $190.81 per TON · qty 3643.0 · bid tab
  • 2026-06-12 · IDOT · Section 72[6RS;(6-1)RS-1] · $130.00 per TON · qty 8927.0 · bid tab
  • 2026-06-12 · IDOT · Section 72[6RS;(6-1)RS-1] · $120.00 per TON · qty 5769.0 · bid tab
  • 2026-06-12 · IDOT · Section 72[6RS;(6-1)RS-1] · $250.00 per TON · qty 142.4 · bid tab
  • 2026-06-12 · IDOT · Section 72[6RS;(6-1)RS-1] · $120.00 per TON · qty 6594.0 · bid tab
(10 most recent of 74 shown; all in the Hubstake feed)
curb gutterEACH7$18.00$8.50 to $110.00
Bids
  • 2026-02-27 · IDOT · Section (8,103)RS-5;[(103B)I]BRR · $18.00 per EACH · qty 21.0 · bid tab
  • 2026-02-27 · IDOT · Section 116N,TS-1 · $15.69 per EACH · qty 58.0 · bid tab
  • 2026-02-27 · IDOT · Section 130RS-7;131RS-6 · $110.00 per EACH · qty 12.0 · bid tab
  • 2026-02-27 · IDOT · Section 130RS-8 · $18.00 per EACH · qty 45.0 · bid tab
  • 2025-08-01 · IDOT · Section (Y,72-6)TS · $15.33 per EACH · qty 67.0 · bid tab
  • 2025-04-25 · IDOT · Section 45RS-8;(46-1)RS-10 · $8.50 per EACH · qty 84.0 · bid tab
  • 2024-06-14 · IDOT · Section [(126)RS-8;(Y)RS-7]CG, MED · $22.00 per EACH · qty 38.0 · bid tab
curb gutterFOOT47$67.78$2.50 to $735.99
Bids
  • 2026-06-12 · IDOT · Section (10R)RS-8 · $118.81 per FOOT · qty 52.0 · bid tab
  • 2026-06-12 · IDOT · Section (10R)RS-8 · $318.27 per FOOT · qty 52.0 · bid tab
  • 2026-06-12 · IDOT · Section (10R)RS-8 · $95.52 per FOOT · qty 164.0 · bid tab
  • 2026-06-12 · IDOT · Section (10R)RS-8 · $262.99 per FOOT · qty 164.0 · bid tab
  • 2026-06-12 · IDOT · Section 72[6RS;(6-1)RS-1] · $10.00 per FOOT · qty 7168.7 · bid tab
  • 2026-02-27 · IDOT · Section (8,103)RS-5;[(103B)I]BRR · $132.35 per FOOT · qty 80.0 · bid tab
  • 2026-02-27 · IDOT · Section (8,103)RS-5;[(103B)I]BRR · $22.00 per FOOT · qty 2511.0 · bid tab
  • 2026-02-27 · IDOT · Section (8,103)RS-5;[(103B)I]BRR · $58.40 per FOOT · qty 2401.0 · bid tab
  • 2026-02-27 · IDOT · Section (8,103)RS-5;[(103B)I]BRR · $132.15 per FOOT · qty 27.0 · bid tab
  • 2026-02-27 · IDOT · Section 116N,TS-1 · $103.29 per FOOT · qty 98.0 · bid tab
(10 most recent of 47 shown; all in the Hubstake feed)
inlet headwallEACH14$243.50$128.31 to $6,550.00
Bids
  • 2026-02-27 · IDOT · Section 116N,TS-1 · $128.31 per EACH · qty 2.0 · bid tab
  • 2026-02-27 · IDOT · Section 72[(7,7-1)RS-3;1RS-5] · $356.13 per EACH · qty 8.0 · bid tab
  • 2026-01-16 · IDOT · Section 22-00112-00-BR · $268.08 per EACH · qty 2.0 · bid tab
  • 2025-08-01 · IDOT · Section (10R-VBY)BR · $200.00 per EACH · qty 6.0 · bid tab
  • 2025-08-01 · IDOT · Section (Y,72-6)TS · $448.28 per EACH · qty 2.0 · bid tab
  • 2025-06-13 · IDOT · Section (15B-1)BP,BRR;(14HB-1)BRR · $6,550.00 per EACH · qty 1.0 · bid tab
  • 2025-06-13 · IDOT · Section (15B-1)BP,BRR;(14HB-1)BRR · $575.00 per EACH · qty 25.0 · bid tab
  • 2025-01-17 · IDOT · Section 23-00042-00-BT · $150.00 per EACH · qty 10.0 · bid tab
  • 2024-11-08 · IDOT · Section (72-3HVB)BR · $237.00 per EACH · qty 2.0 · bid tab
  • 2024-11-08 · IDOT · Section 19-00115-01-PV · $150.00 per EACH · qty 121.0 · bid tab
(10 most recent of 14 shown; all in the Hubstake feed)
manholeEACH4$1,625.00$1,000.00 to $2,950.00
Bids
  • 2026-06-12 · IDOT · Section (72-7)L-1;[72(8,9);90-11]L-2 · $2,950.00 per EACH · qty 12.0 · bid tab
  • 2026-02-27 · IDOT · Section 72[(7,7-1)RS-3;1RS-5] · $1,650.00 per EACH · qty 3.0 · bid tab
  • 2025-08-01 · IDOT · Section (10R-VBY)BR · $1,600.00 per EACH · qty 1.0 · bid tab
  • 2025-01-17 · IDOT · Section 23-00042-00-BT · $1,000.00 per EACH · qty 6.0 · bid tab
sidewalkEACH1$1,000.00$1,000.00 to $1,000.00
Bids
  • 2024-04-26 · IDOT · Section 20-00387-00-PV · $1,000.00 per EACH · qty 1.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.