| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | SQ YD | 73 | $13.09 | $2.20 to $530.56 | Bids- 2026-06-12 · IDOT · Section 57-7RS-4,57-8RS-3 · $14.87 per SQ YD · qty 15128.0 · bid tab
- 2026-06-12 · IDOT · Section 57-7RS-4,57-8RS-3 · $8.61 per SQ YD · qty 42868.0 · bid tab
- 2026-06-12 · IDOT · Section 57-7RS-4,57-8RS-3 · $26.66 per SQ YD · qty 1089.0 · bid tab
- 2026-06-12 · IDOT · Section 57-7RS-4,57-8RS-3 · $8.45 per SQ YD · qty 11313.0 · bid tab
- 2026-06-12 · IDOT · Section 57-7RS-4,57-8RS-3 · $7.50 per SQ YD · qty 145836.0 · bid tab
- 2026-06-12 · IDOT · Section LEROY,TOWANDA,BLOOM IMP 2026-1 · $13.25 per SQ YD · qty 2795.0 · bid tab
- 2026-04-24 · IDOT · Section (120)RS-1 · $24.77 per SQ YD · qty 2558.0 · bid tab
- 2026-04-24 · IDOT · Section (120)RS-1 · $5.50 per SQ YD · qty 109540.0 · bid tab
- 2026-04-24 · IDOT · Section (120)RS-1 · $530.56 per SQ YD · qty 40.0 · bid tab
- 2026-04-24 · IDOT · Section (57-20(1),21,22)RS-4 · $5.25 per SQ YD · qty 332447.0 · bid tab
(10 most recent of 73 shown; all in the Hubstake feed) |
| asphalt pavement | TON | 84 | $195.00 | $0.01 to $675.00 | Bids- 2026-06-12 · IDOT · Section 57-7RS-4,57-8RS-3 · $225.11 per TON · qty 962.0 · bid tab
- 2026-06-12 · IDOT · Section 57-7RS-4,57-8RS-3 · $0.01 per TON · qty 290.0 · bid tab
- 2026-06-12 · IDOT · Section 57-7RS-4,57-8RS-3 · $235.51 per TON · qty 825.0 · bid tab
- 2026-06-12 · IDOT · Section 57-7RS-4,57-8RS-3 · $165.20 per TON · qty 27440.0 · bid tab
- 2026-06-12 · IDOT · Section 57-7RS-4,57-8RS-3 · $160.33 per TON · qty 12403.0 · bid tab
- 2026-06-12 · IDOT · Section 57-7RS-4,57-8RS-3 · $374.43 per TON · qty 52.0 · bid tab
- 2026-06-12 · IDOT · Section LEROY,TOWANDA,BLOOM IMP 2026-1 · $159.00 per TON · qty 2570.0 · bid tab
- 2026-06-12 · IDOT · Section LEROY,TOWANDA,BLOOM IMP 2026-1 · $158.00 per TON · qty 1034.0 · bid tab
- 2026-04-24 · IDOT · Section (120)RS-1 · $151.24 per TON · qty 9226.0 · bid tab
- 2026-04-24 · IDOT · Section (120)RS-1 · $148.61 per TON · qty 7688.0 · bid tab
(10 most recent of 84 shown; all in the Hubstake feed) |
| concrete pavement | SQ YD | 1 | $8.00 | $8.00 to $8.00 | Bids- 2024-03-08 · IDOT · Section 20-00271-00-PV · $8.00 per SQ YD · qty 13988.0 · bid tab
|
| curb gutter | EACH | 2 | $746.57 | $48.00 to $1,445.14 | Bids- 2026-04-24 · IDOT · Section CM PATCHING 2026-1 · $48.00 per EACH · qty 7.0 · bid tab
- 2025-08-01 · IDOT · Section 24-00360-01-PV · $1,445.14 per EACH · qty 6.0 · bid tab
|
| curb gutter | FOOT | 70 | $83.09 | $2.25 to $402.47 | Bids- 2026-04-24 · IDOT · Section 109RS-4 · $9.50 per FOOT · qty 12508.0 · bid tab
- 2026-04-24 · IDOT · Section 109RS-4 · $2.25 per FOOT · qty 1166.0 · bid tab
- 2026-04-24 · IDOT · Section 109RS-4 · $80.00 per FOOT · qty 14266.0 · bid tab
- 2026-02-27 · IDOT · Section (57-3)BR · $15.00 per FOOT · qty 462.0 · bid tab
- 2026-02-27 · IDOT · Section 24-00170-01-RS · $40.06 per FOOT · qty 460.0 · bid tab
- 2026-02-27 · IDOT · Section 24-00170-01-RS · $144.81 per FOOT · qty 145.0 · bid tab
- 2026-02-27 · IDOT · Section 24-00170-01-RS · $96.97 per FOOT · qty 150.0 · bid tab
- 2025-11-07 · IDOT · Section (4)RS1,(109)RS3 · $32.27 per FOOT · qty 7162.0 · bid tab
- 2025-11-07 · IDOT · Section (4)RS1,(109)RS3 · $90.00 per FOOT · qty 6896.0 · bid tab
- 2025-11-07 · IDOT · Section (4)RS1,(109)RS3 · $105.00 per FOOT · qty 5456.0 · bid tab
(10 most recent of 70 shown; all in the Hubstake feed) |
| fire hydrant | EACH | 1 | $9,630.00 | $9,630.00 to $9,630.00 | Bids- 2025-08-01 · IDOT · Section 24-00360-01-PV · $9,630.00 per EACH · qty 4.0 · bid tab
|
| inlet headwall | EACH | 12 | $278.18 | $150.00 to $5,500.00 | Bids- 2026-02-27 · IDOT · Section (57-10HB)BR-1 · $5,500.00 per EACH · qty 2.0 · bid tab
- 2025-09-19 · IDOT · Section (104,121)DR · $375.00 per EACH · qty 8.0 · bid tab
- 2025-09-19 · IDOT · Section (FR)RS-3 · $254.09 per EACH · qty 25.0 · bid tab
- 2025-08-01 · IDOT · Section 24-00360-01-PV · $218.53 per EACH · qty 14.0 · bid tab
- 2025-06-13 · IDOT · Section 20-00271-01-PV · $875.23 per EACH · qty 1.0 · bid tab
- 2025-06-13 · IDOT · Section 20-00271-01-PV · $256.36 per EACH · qty 6.0 · bid tab
- 2025-03-07 · IDOT · Section 23-00001-06-BT · $200.94 per EACH · qty 11.0 · bid tab
- 2025-03-07 · IDOT · Section 23-00018-00-BT · $300.00 per EACH · qty 6.0 · bid tab
- 2024-03-08 · IDOT · Section (129)RS-4 · $1,800.00 per EACH · qty 17.0 · bid tab
- 2024-03-08 · IDOT · Section 20-00271-00-PV · $150.00 per EACH · qty 192.0 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed) |
| manhole | EACH | 6 | $3,295.10 | $565.00 to $20,805.99 | Bids- 2025-09-19 · IDOT · Section (FR)RS-3 · $3,990.19 per EACH · qty 1.0 · bid tab
- 2025-08-01 · IDOT · Section 24-00360-01-PV · $1,605.00 per EACH · qty 6.0 · bid tab
- 2025-08-01 · IDOT · Section 24-00360-01-PV · $20,805.99 per EACH · qty 1.0 · bid tab
- 2025-08-01 · IDOT · Section 24-00360-01-PV · $14,212.83 per EACH · qty 2.0 · bid tab
- 2024-11-08 · IDOT · Section 16-00360-00-PV · $2,600.00 per EACH · qty 6.0 · bid tab
- 2024-03-08 · IDOT · Section 20-00271-00-PV · $565.00 per EACH · qty 18.0 · bid tab
|