Site-work prices, Johnson County, IL
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | SQ YD | 17 | $8.00 | $1.20 to $50.00 | Bids- 2026-04-24 · IDOT · Section D9 RESURFACE 2026-2 · $5.50 per SQ YD · qty 5680.0 · bid tab
- 2025-06-13 · IDOT · Section 107RS-6 · $4.00 per SQ YD · qty 11632.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $1.25 per SQ YD · qty 3871.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $1.20 per SQ YD · qty 137432.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $15.00 per SQ YD · qty 818.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $20.00 per SQ YD · qty 2066.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $50.00 per SQ YD · qty 480.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $2.05 per SQ YD · qty 6728.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $2.20 per SQ YD · qty 7125.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $18.00 per SQ YD · qty 6325.0 · bid tab
(10 most recent of 17 shown; all in the Hubstake feed) |
| asphalt pavement | TON | 15 | $118.00 | $75.00 to $555.00 | Bids- 2026-04-24 · IDOT · Section D9 RESURFACE 2026-2 · $200.00 per TON · qty 5.0 · bid tab
- 2026-04-24 · IDOT · Section D9 RESURFACE 2026-2 · $132.00 per TON · qty 481.0 · bid tab
- 2026-04-24 · IDOT · Section D9 RESURFACE 2026-2 · $131.00 per TON · qty 477.0 · bid tab
- 2025-06-13 · IDOT · Section 107RS-6 · $118.00 per TON · qty 980.0 · bid tab
- 2025-06-13 · IDOT · Section 107RS-6 · $120.00 per TON · qty 980.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $80.00 per TON · qty 12507.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $145.00 per TON · qty 223.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $77.00 per TON · qty 10143.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $555.00 per TON · qty 121.0 · bid tab
- 2024-12-13 · IDOT · Section 113RS-4 · $500.00 per TON · qty 27.0 · bid tab
(10 most recent of 15 shown; all in the Hubstake feed) |
| curb gutter | FOOT | 4 | $38.00 | $15.00 to $95.00 | Bids- 2025-06-13 · IDOT · Section 107RS-6 · $15.00 per FOOT · qty 10.0 · bid tab
- 2025-06-13 · IDOT · Section 107RS-6 · $95.00 per FOOT · qty 520.0 · bid tab
- 2025-06-13 · IDOT · Section 107RS-6 · $30.00 per FOOT · qty 511.0 · bid tab
- 2025-03-07 · IDOT · Section D9 RESURFACE 2025-1 · $46.00 per FOOT · qty 770.0 · bid tab
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.