Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementSQ YD27$38.00$2.28 to $713.05
Bids
  • 2026-01-16 · IDOT · Section (106,107)RS-3 · $5.20 per SQ YD · qty 302.0 · bid tab
  • 2026-01-16 · IDOT · Section (106,107)RS-3 · $4.37 per SQ YD · qty 46444.0 · bid tab
  • 2026-01-16 · IDOT · Section (106,107)RS-3 · $8.27 per SQ YD · qty 5964.0 · bid tab
  • 2026-01-16 · IDOT · Section (107Z)RS-4 · $6.50 per SQ YD · qty 18303.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $177.50 per SQ YD · qty 1967.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $237.00 per SQ YD · qty 806.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $40.80 per SQ YD · qty 2746.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $35.60 per SQ YD · qty 70575.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $68.70 per SQ YD · qty 170.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $174.00 per SQ YD · qty 1026.0 · bid tab
(10 most recent of 27 shown; all in the Hubstake feed)
asphalt pavementTON24$200.19$107.01 to $690.30
Bids
  • 2026-01-16 · IDOT · Section (106,107)RS-3 · $142.55 per TON · qty 5903.0 · bid tab
  • 2026-01-16 · IDOT · Section (106,107)RS-3 · $151.02 per TON · qty 5166.0 · bid tab
  • 2026-01-16 · IDOT · Section (106,107)RS-3 · $521.07 per TON · qty 62.0 · bid tab
  • 2026-01-16 · IDOT · Section (107Z)RS-4 · $392.16 per TON · qty 32.0 · bid tab
  • 2026-01-16 · IDOT · Section (107Z)RS-4 · $149.27 per TON · qty 1706.0 · bid tab
  • 2026-01-16 · IDOT · Section (107Z)RS-4 · $153.22 per TON · qty 1949.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $268.50 per TON · qty 609.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $215.50 per TON · qty 373.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $228.00 per TON · qty 560.0 · bid tab
  • 2025-09-19 · IDOT · Section (105)RS-3 · $251.36 per TON · qty 431.0 · bid tab
(10 most recent of 24 shown; all in the Hubstake feed)
curb gutterFOOT13$93.00$10.90 to $200.00
Bids
  • 2026-06-12 · IDOT · Section 23-00022-00-PV · $82.00 per FOOT · qty 320.0 · bid tab
  • 2026-06-12 · IDOT · Section 23-00022-00-PV · $13.00 per FOOT · qty 290.0 · bid tab
  • 2026-06-12 · IDOT · Section 23-00022-00-PV · $93.00 per FOOT · qty 124.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $102.00 per FOOT · qty 798.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $10.90 per FOOT · qty 1981.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $131.50 per FOOT · qty 54.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $143.00 per FOOT · qty 42.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $48.00 per FOOT · qty 1994.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $11.90 per FOOT · qty 1157.0 · bid tab
  • 2025-09-19 · IDOT · Section (105)RS-3 · $143.86 per FOOT · qty 44.0 · bid tab
(10 most recent of 13 shown; all in the Hubstake feed)
inlet headwallEACH4$402.64$275.00 to $12,180.00
Bids
  • 2026-06-12 · IDOT · Section D7 DEMOLITION 2025-1 · $275.00 per EACH · qty 12.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $301.00 per EACH · qty 21.0 · bid tab
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $12,180.00 per EACH · qty 7.0 · bid tab
  • 2025-09-19 · IDOT · Section (26-0,1)MED · $504.28 per EACH · qty 3.0 · bid tab
lime cement stabilizationTON1$165.00$165.00 to $165.00
Bids
  • 2026-01-16 · IDOT · Section (25-1)R-BR · $165.00 per TON · qty 1948.1 · bid tab
manholeEACH1$375.00$375.00 to $375.00
Bids
  • 2026-06-12 · IDOT · Section 23-00022-00-PV · $375.00 per EACH · qty 9.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.