Site-work prices, Cook County, IL

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementSQ YD659$15.00$0.01 to $285.00
Bids
  • 2026-09-18 · IDOT · Section 2024-951-RS,SW · $4.10 per SQ YD · qty 28619.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-951-RS,SW · $145.00 per SQ YD · qty 14.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-951-RS,SW · $195.00 per SQ YD · qty 7.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-951-RS,SW · $1.00 per SQ YD · qty 622.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-951-RS,SW · $6.40 per SQ YD · qty 58516.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0341 23 SMART · $12.00 per SQ YD · qty 1185.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0341 23 SMART · $23.00 per SQ YD · qty 1543.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0341 23 SMART · $4.05 per SQ YD · qty 197522.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0397 23 SMART · $2.25 per SQ YD · qty 90135.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0397 23 SMART · $0.01 per SQ YD · qty 931.0 · bid tab
(10 most recent of 659 shown; all in the Hubstake feed)
asphalt pavementTON575$125.00$0.01 to $8,490.84
Bids
  • 2026-09-18 · IDOT · Section 2024-1043-RS · $75.00 per TON · qty 4996.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-1043-RS · $145.00 per TON · qty 8902.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-951-RS,SW · $96.15 per TON · qty 6554.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-951-RS,SW · $400.00 per TON · qty 3.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-951-RS,SW · $130.85 per TON · qty 1181.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-951-RS,SW · $98.35 per TON · qty 8139.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0341 23 SMART · $113.00 per TON · qty 20064.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0397 23 SMART · $400.00 per TON · qty 20.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0397 23 SMART · $122.00 per TON · qty 8834.0 · bid tab
  • 2026-09-18 · IDOT · Section FAU 2722 23 SMART · $100.00 per TON · qty 4849.0 · bid tab
(10 most recent of 575 shown; all in the Hubstake feed)
concrete pavementFOOT7$0.75$0.11 to $18.00
Bids
  • 2026-07-31 · IDOT · Section FAP 0344A 23 C&J · $0.11 per FOOT · qty 21082.0 · bid tab
  • 2026-04-24 · IDOT · Section (0404.2-1B) BD,BJR 25 · $18.00 per FOOT · qty 95.0 · bid tab
  • 2026-04-24 · IDOT · Section 2025-2106-RS · $0.15 per FOOT · qty 5975.0 · bid tab
  • 2025-04-25 · IDOT · Section 2019-107-RS&SW · $0.70 per FOOT · qty 11061.0 · bid tab
  • 2024-08-02 · IDOT · Section 2020-005-BR · $0.75 per FOOT · qty 40000.0 · bid tab
  • 2024-04-26 · IDOT · Section 2023 ETP YARD PARKING · $2.50 per FOOT · qty 868.0 · bid tab
  • 2023-11-17 · IDOT · Section FAP 0351 22 RS · $2.50 per FOOT · qty 3103.0 · bid tab
concrete pavementSQ YD2$207.50$150.00 to $265.00
Bids
  • 2025-06-13 · IDOT · Section CHICAGO EXECUTIVE · $150.00 per SQ YD · qty 1660.0 · bid tab
  • 2024-08-02 · IDOT · Section FAI 90 23 TBR · $265.00 per SQ YD · qty 88.0 · bid tab
curb gutterEACH2$22.50$20.00 to $25.00
Bids
  • 2025-08-01 · IDOT · Section 2021-060-SW-TS&N · $20.00 per EACH · qty 18.0 · bid tab
  • 2025-03-07 · IDOT · Section 22-00112-00-RS · $25.00 per EACH · qty 14.0 · bid tab
curb gutterFOOT761$46.00$1.00 to $600.00
Bids
  • 2026-09-18 · IDOT · Section 2024-1043-RS · $2.50 per FOOT · qty 1903.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-1043-RS · $60.00 per FOOT · qty 225.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-1043-RS · $55.00 per FOOT · qty 1678.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-951-RS,SW · $75.00 per FOOT · qty 2593.0 · bid tab
  • 2026-09-18 · IDOT · Section 2024-951-RS,SW · $140.00 per FOOT · qty 10.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0341 23 SMART · $64.00 per FOOT · qty 2604.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0341 23 SMART · $37.50 per FOOT · qty 20112.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0341 23 SMART · $8.20 per FOOT · qty 20493.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0341 23 SMART · $66.00 per FOOT · qty 4048.0 · bid tab
  • 2026-09-18 · IDOT · Section FAP 0397 23 SMART · $44.00 per FOOT · qty 3801.0 · bid tab
(10 most recent of 761 shown; all in the Hubstake feed)
curb gutterSQ FT2$109.10$50.00 to $168.20
Bids
  • 2025-11-07 · IDOT · Section 19-00035-00-SP · $168.20 per SQ FT · qty 359.0 · bid tab
  • 2025-09-19 · IDOT · Section 24-00093-00-SW · $50.00 per SQ FT · qty 91.0 · bid tab
excavation embankmentCU YD2$75.00$75.00 to $75.00
Bids
  • 2025-06-13 · IDOT · Section CHICAGO EXECUTIVE · $75.00 per CU YD · qty 6130.0 · bid tab
  • 2025-06-13 · IDOT · Section CHICAGO EXECUTIVE · $75.00 per CU YD · qty 1110.0 · bid tab
fire hydrantEACH1$2,600.00$2,600.00 to $2,600.00
Bids
  • 2024-09-20 · IDOT · Section 20-00108-02-RS · $2,600.00 per EACH · qty 15.0 · bid tab
fire hydrantFOOT6$1,962.50$852.00 to $2,050.00
Bids
  • 2026-02-27 · IDOT · Section 23-00146-00-PV · $1,975.00 per FOOT · qty 19.0 · bid tab
  • 2026-02-27 · IDOT · Section 25-00149-01-RS · $1,950.00 per FOOT · qty 9.0 · bid tab
  • 2026-02-27 · IDOT · Section 25-00149-02-RS · $2,050.00 per FOOT · qty 14.0 · bid tab
  • 2025-09-19 · IDOT · Section 20-00073-01-PV · $852.00 per FOOT · qty 5.0 · bid tab
  • 2024-09-20 · IDOT · Section 10-00055-02-WR · $1,400.61 per FOOT · qty 10.0 · bid tab
  • 2024-09-20 · IDOT · Section 20-00108-02-RS · $2,000.00 per FOOT · qty 10.0 · bid tab
flexible baseSQ YD3$30.00$15.00 to $62.15
Bids
  • 2025-06-13 · IDOT · Section CHICAGO EXECUTIVE · $30.00 per SQ YD · qty 1450.0 · bid tab
  • 2025-06-13 · IDOT · Section CHICAGO EXECUTIVE · $15.00 per SQ YD · qty 1750.0 · bid tab
  • 2025-01-17 · IDOT · Section 21-00134-00-RS · $62.15 per SQ YD · qty 750.0 · bid tab
flexible baseTON1$305.00$305.00 to $305.00
Bids
  • 2025-06-13 · IDOT · Section CHICAGO EXECUTIVE · $305.00 per TON · qty 500.0 · bid tab
inlet headwallEACH38$262.50$56.01 to $42,000.00
Bids
  • 2026-07-31 · IDOT · Section FAI 80 23 BRIDGE REPLACEMENT 2 · $72.60 per EACH · qty 3.0 · bid tab
  • 2026-07-31 · IDOT · Section FAI 80 23 BRIDGE REPLACEMENT 2 · $10,000.00 per EACH · qty 4.0 · bid tab
  • 2026-07-31 · IDOT · Section FAU 2843 22 CR · $154.00 per EACH · qty 7.0 · bid tab
  • 2026-06-12 · IDOT · Section 2020-142-C&DR · $132.00 per EACH · qty 102.0 · bid tab
  • 2026-06-12 · IDOT · Section 2023 VAR DRAINAGE · $121.00 per EACH · qty 15.0 · bid tab
  • 2026-06-12 · IDOT · Section 23-P4062-00-BT · $121.00 per EACH · qty 2.0 · bid tab
  • 2026-06-12 · IDOT · Section FAU 1593 22 BJ · $350.00 per EACH · qty 8.0 · bid tab
  • 2026-06-12 · IDOT · Section WILLIAM POWERS PAVING · $350.00 per EACH · qty 6.0 · bid tab
  • 2026-04-24 · IDOT · Section (1010B-89) BDR,BJR 25 · $200.00 per EACH · qty 9.0 · bid tab
  • 2026-04-24 · IDOT · Section 2019-161-W · $300.00 per EACH · qty 6.0 · bid tab
(10 most recent of 38 shown; all in the Hubstake feed)
manholeEACH81$1,750.00$143.71 to $105,223.89
Bids
  • 2026-07-31 · IDOT · Section 22-00078-00-RS · $1,750.00 per EACH · qty 1.0 · bid tab
  • 2026-07-31 · IDOT · Section FAI 80 23 BRIDGE REPLACEMENT 2 · $7,095.12 per EACH · qty 3.0 · bid tab
  • 2026-07-31 · IDOT · Section FAI 80 23 BRIDGE REPLACEMENT 2 · $1,400.00 per EACH · qty 2.0 · bid tab
  • 2026-07-31 · IDOT · Section FAU 2843 22 CR · $1,500.00 per EACH · qty 1.0 · bid tab
  • 2026-06-12 · IDOT · Section (0404-316-HB) BR 24 · $105,223.89 per EACH · qty 6.0 · bid tab
  • 2026-06-12 · IDOT · Section FAI 290 22 STRUCTURE 1 · $143.71 per EACH · qty 44.0 · bid tab
  • 2026-06-12 · IDOT · Section FAI 290 22 STRUCTURE 1 · $13,307.65 per EACH · qty 1.0 · bid tab
  • 2026-04-24 · IDOT · Section 2019-161-W · $12,720.00 per EACH · qty 4.0 · bid tab
  • 2026-04-24 · IDOT · Section 21-00174-00-BR · $3,800.00 per EACH · qty 1.0 · bid tab
  • 2026-02-27 · IDOT · Section 23-00114-00-CH · $1,365.00 per EACH · qty 6.0 · bid tab
(10 most recent of 81 shown; all in the Hubstake feed)
sidewalkEACH2$2,119.24$650.93 to $3,587.54
Bids
  • 2026-04-24 · IDOT · Section 2025-1076-I · $650.93 per EACH · qty 15.0 · bid tab
  • 2025-06-13 · IDOT · Section 2024-965-TS · $3,587.54 per EACH · qty 26.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.