| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | SY | 1 | $25.05 | $25.05 to $25.05 | Bids- 2026-01-21 · Iowa DOT · 81-C081-085 · $25.05 per SY · qty 1644.33 · bid tab
|
| asphalt pavement | TON | 2 | $44.22 | $44.22 to $44.22 | Bids- 2026-06-16 · Iowa DOT · 81-1754-021 · $44.22 per TON · qty 13320.0 · bid tab
- 2026-06-16 · Iowa DOT · 81-1754-021 · $44.22 per TON · qty 8079.3 · bid tab
|
| concrete pavement | EACH | 2 | $1.00 | $1.00 to $1.00 | Bids- 2024-11-19 · Iowa DOT · 81-C081-084 · $1.00 per EACH · qty 207963.1 · bid tab
- 2024-11-19 · Iowa DOT · 81-C081-084 · $1.00 per EACH · qty 133309.7 · bid tab
|
| concrete pavement | LS | 1 | $500.00 | $500.00 to $500.00 | Bids- 2024-11-19 · Iowa DOT · 81-C081-084 · $500.00 per LS · qty 1.0 · bid tab
|
| concrete pavement | SY | 2 | $66.50 | $33.01 to $100.00 | Bids- 2026-02-17 · Iowa DOT · 81-4157-605 · $100.00 per SY · qty 371.1 · bid tab
- 2024-11-19 · Iowa DOT · 81-C081-084 · $33.01 per SY · qty 177746.2 · bid tab
|
| excavation embankment | CY | 9 | $13.81 | $3.07 to $31.43 | Bids- 2026-06-16 · Iowa DOT · 81-1754-021 · $25.00 per CY · qty 254.0 · bid tab
- 2026-02-17 · Iowa DOT · 81-4157-605 · $4.50 per CY · qty 1624.0 · bid tab
- 2026-01-21 · Iowa DOT · 81-C081-085 · $31.43 per CY · qty 52.5 · bid tab
- 2025-08-19 · Iowa DOT · 81-C081-078 · $13.81 per CY · qty 8955.0 · bid tab
- 2025-08-19 · Iowa DOT · 81-C081-078 · $3.07 per CY · qty 1610.0 · bid tab
- 2025-08-19 · Iowa DOT · 81-C081-078 · $4.20 per CY · qty 1565.0 · bid tab
- 2024-11-19 · Iowa DOT · 81-C081-084 · $18.70 per CY · qty 24418.47 · bid tab
- 2024-11-19 · Iowa DOT · 81-C081-084 · $3.55 per CY · qty 64419.0 · bid tab
- 2024-01-17 · Iowa DOT · 81-C081-094 · $25.00 per CY · qty 857.7 · bid tab
|
| lime cement stabilization | ACRE | 3 | $350.00 | $250.00 to $500.00 | Bids- 2026-02-17 · Iowa DOT · 81-4157-605 · $350.00 per ACRE · qty 2.8 · bid tab
- 2025-08-19 · Iowa DOT · 81-C081-078 · $500.00 per ACRE · qty 5.9 · bid tab
- 2024-11-19 · Iowa DOT · 81-C081-084 · $250.00 per ACRE · qty 54.06 · bid tab
|
| sidewalk | SY | 1 | $55.86 | $55.86 to $55.86 | Bids- 2024-11-19 · Iowa DOT · 81-C081-084 · $55.86 per SY · qty 111.1 · bid tab
|
| storm pipe 18-inch | LF | 1 | $64.22 | $64.22 to $64.22 | Bids- 2025-08-19 · Iowa DOT · 81-C081-078 · $64.22 per LF · qty 282.0 · bid tab
|
| storm pipe 24-inch | LF | 2 | $80.95 | $74.50 to $87.40 | Bids- 2025-08-19 · Iowa DOT · 81-C081-078 · $87.40 per LF · qty 204.0 · bid tab
- 2024-11-19 · Iowa DOT · 81-C081-084 · $74.50 per LF · qty 1365.0 · bid tab
|
| storm pipe 30-inch | LF | 2 | $92.50 | $85.00 to $100.00 | Bids- 2026-02-17 · Iowa DOT · 81-4157-605 · $85.00 per LF · qty 100.0 · bid tab
- 2024-11-19 · Iowa DOT · 81-C081-084 · $100.00 per LF · qty 282.0 · bid tab
|
| storm pipe 36-inch | LF | 1 | $141.00 | $141.00 to $141.00 | Bids- 2024-11-19 · Iowa DOT · 81-C081-084 · $141.00 per LF · qty 238.0 · bid tab
|