Site-work prices, Poweshiek, Tama County, IA
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | SY | 2 | $56.35 | $29.35 to $83.35 | |
| curb gutter | LF | 1 | $37.00 | $37.00 to $37.00 | Bids
|
| excavation embankment | CY | 2 | $7.60 | $3.20 to $12.00 | |
| lime cement stabilization | ACRE | 1 | $275.00 | $275.00 to $275.00 | Bids
|
| sidewalk | SY | 1 | $103.35 | $103.35 to $103.35 | Bids
|
| storm pipe 24-inch | LF | 2 | $196.25 | $42.50 to $350.00 | |
| storm pipe 30-inch | LF | 1 | $250.00 | $250.00 to $250.00 | Bids
|
| storm pipe 36-inch | LF | 1 | $270.00 | $270.00 to $270.00 | Bids
|
| storm pipe 42-inch | LF | 1 | $365.00 | $365.00 to $365.00 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.