Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | SY | 1 | $221.57 | $221.57 to $221.57 | Bids- 2026-10-20 · Iowa DOT · 61-0924-030 · $221.57 per SY · qty 192.3 · bid tab
|
| asphalt pavement | TON | 1 | $60.25 | $60.25 to $60.25 | Bids- 2025-01-22 · Iowa DOT · 61-C061-134 · $60.25 per TON · qty 674.82 · bid tab
|
| concrete pavement | SY | 2 | $124.64 | $89.00 to $160.27 | Bids- 2026-07-21 · Iowa DOT · 61-C061-131 · $160.27 per SY · qty 428.0 · bid tab
- 2025-05-20 · Iowa DOT · 61-C061-129 · $89.00 per SY · qty 1328.1 · bid tab
|
| excavation embankment | CY | 12 | $10.44 | $5.00 to $30.38 | Bids- 2026-10-20 · Iowa DOT · 61-0924-030 · $10.38 per CY · qty 176.9 · bid tab
- 2026-10-20 · Iowa DOT · 61-0924-030 · $30.38 per CY · qty 51.1 · bid tab
- 2026-07-21 · Iowa DOT · 61-C061-130 · $10.30 per CY · qty 327.0 · bid tab
- 2026-07-21 · Iowa DOT · 61-C061-131 · $22.00 per CY · qty 2350.0 · bid tab
- 2026-07-21 · Iowa DOT · 61-C061-131 · $5.00 per CY · qty 4804.0 · bid tab
- 2025-12-16 · Iowa DOT · 61-8497-604 · $10.00 per CY · qty 285.0 · bid tab
- 2025-12-16 · Iowa DOT · 61-8497-604 · $25.00 per CY · qty 175.0 · bid tab
- 2025-06-17 · Iowa DOT · 61-C061-132 · $8.00 per CY · qty 554.28 · bid tab
- 2025-06-17 · Iowa DOT · 61-C061-132 · $15.00 per CY · qty 1840.19 · bid tab
- 2025-05-20 · Iowa DOT · 61-C061-129 · $7.75 per CY · qty 1539.0 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed) |
| lime cement stabilization | ACRE | 4 | $340.00 | $300.00 to $350.00 | Bids- 2026-07-21 · Iowa DOT · 61-C061-130 · $350.00 per ACRE · qty 1.4 · bid tab
- 2026-07-21 · Iowa DOT · 61-C061-131 · $300.00 per ACRE · qty 2.2 · bid tab
- 2025-06-17 · Iowa DOT · 61-C061-132 · $330.00 per ACRE · qty 1.32 · bid tab
- 2025-05-20 · Iowa DOT · 61-C061-129 · $350.00 per ACRE · qty 2.3 · bid tab
|
| storm pipe 18-inch | LF | 1 | $115.00 | $115.00 to $115.00 | Bids- 2025-05-20 · Iowa DOT · 61-C061-129 · $115.00 per LF · qty 74.0 · bid tab
|
| storm pipe 60-inch | LF | 1 | $165.00 | $165.00 to $165.00 | Bids- 2025-01-22 · Iowa DOT · 61-C061-134 · $165.00 per LF · qty 54.0 · bid tab
|