Site-work prices, Iowa County, IA

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementSY3$29.95$2.04 to $58.55
Bids
  • 2026-10-20 · Iowa DOT · 48-1492-066 · $58.55 per SY · qty 867.7 · bid tab
  • 2026-10-20 · Iowa DOT · 48-1492-066 · $29.95 per SY · qty 20743.3 · bid tab
  • 2026-02-17 · Iowa DOT · 48-C048-105 · $2.04 per SY · qty 59926.0 · bid tab
asphalt pavementTON8$56.35$51.80 to $494.70
Bids
  • 2026-10-20 · Iowa DOT · 48-1492-066 · $55.05 per TON · qty 2995.5 · bid tab
  • 2026-02-17 · Iowa DOT · 48-C048-105 · $494.70 per TON · qty 197.0 · bid tab
  • 2025-10-22 · Iowa DOT · 48-0806-530 · $55.95 per TON · qty 17934.376 · bid tab
  • 2025-04-15 · Iowa DOT · 48-8427-603-A · $93.00 per TON · qty 791.203 · bid tab
  • 2025-04-15 · Iowa DOT · 48-8427-603-A · $96.35 per TON · qty 667.382 · bid tab
  • 2025-03-18 · Iowa DOT · 48-102 · $56.75 per TON · qty 860.0 · bid tab
  • 2024-01-17 · Iowa DOT · 48-C048-098 · $52.30 per TON · qty 3945.0 · bid tab
  • 2024-01-17 · Iowa DOT · 48-C048-098 · $51.80 per TON · qty 1645.0 · bid tab
concrete pavementEACH2$1.00$1.00 to $1.00
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $1.00 per EACH · qty 26550.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $1.00 per EACH · qty 41418.0 · bid tab
concrete pavementSY2$69.81$68.00 to $71.61
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $71.61 per SY · qty 27635.4 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $68.00 per SY · qty 7764.4 · bid tab
curb gutterEACH1$20.00$20.00 to $20.00
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $20.00 per EACH · qty 10.0 · bid tab
curb gutterLF2$32.50$15.00 to $50.00
Bids
  • 2025-04-15 · Iowa DOT · 48-8427-603-A · $50.00 per LF · qty 81.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $15.00 per LF · qty 58.0 · bid tab
excavation embankmentCY6$13.45$3.55 to $100.00
Bids
  • 2026-10-20 · Iowa DOT · 48-1492-066 · $100.00 per CY · qty 59.3 · bid tab
  • 2026-02-17 · Iowa DOT · 48-C048-103 · $17.50 per CY · qty 672.0 · bid tab
  • 2026-02-17 · Iowa DOT · 48-C048-104 · $8.35 per CY · qty 645.0 · bid tab
  • 2025-10-22 · Iowa DOT · 48-0806-530 · $28.00 per CY · qty 9279.9 · bid tab
  • 2024-12-17 · Iowa DOT · 48-99 · $9.40 per CY · qty 725.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $3.55 per CY · qty 20583.0 · bid tab
lime cement stabilizationACRE1$200.00$200.00 to $200.00
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $200.00 per ACRE · qty 20.0 · bid tab
lime cement stabilizationSY1$3.10$3.10 to $3.10
Bids
  • 2024-01-17 · Iowa DOT · 48-C048-098 · $3.10 per SY · qty 435.0 · bid tab
manholeEACH2$3,343.00$886.00 to $5,800.00
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $5,800.00 per EACH · qty 6.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $886.00 per EACH · qty 7.0 · bid tab
sewer main 10-inchLF1$65.00$65.00 to $65.00
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $65.00 per LF · qty 164.9 · bid tab
sewer main 12-inchLF1$72.00$72.00 to $72.00
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $72.00 per LF · qty 990.9 · bid tab
sidewalkEACH4$6,072.50$1,780.00 to $9,500.00
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $4,205.00 per EACH · qty 1.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $1,780.00 per EACH · qty 2.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $9,500.00 per EACH · qty 1.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $7,940.00 per EACH · qty 9.0 · bid tab
sidewalkSY3$103.79$63.95 to $116.23
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $116.23 per SY · qty 103.5 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $103.79 per SY · qty 172.4 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $63.95 per SY · qty 1220.0 · bid tab
storm pipe 15-inchLF1$66.00$66.00 to $66.00
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $66.00 per LF · qty 1091.0 · bid tab
storm pipe 18-inchLF1$82.00$82.00 to $82.00
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $82.00 per LF · qty 42.0 · bid tab
storm pipe 24-inchLF3$82.50$72.50 to $125.00
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $72.50 per LF · qty 236.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $82.50 per LF · qty 286.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $125.00 per LF · qty 24.0 · bid tab
storm pipe 30-inchLF2$128.50$128.00 to $129.00
Bids
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $129.00 per LF · qty 252.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $128.00 per LF · qty 48.0 · bid tab
storm pipe 36-inchLF3$150.00$100.00 to $340.00
Bids
  • 2026-10-20 · Iowa DOT · 48-1492-066 · $340.00 per LF · qty 43.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $100.00 per LF · qty 192.0 · bid tab
  • 2024-02-20 · Iowa DOT · 48-0806-483 · $150.00 per LF · qty 31.0 · bid tab