| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | SY | 3 | $51.47 | $40.48 to $53.94 | Bids- 2025-02-18 · Iowa DOT · 20-0692-033 · $53.94 per SY · qty 110.0 · bid tab
- 2025-02-18 · Iowa DOT · 20-0692-033 · $51.47 per SY · qty 1647.8 · bid tab
- 2025-02-18 · Iowa DOT · 20-0692-033 · $40.48 per SY · qty 39701.8 · bid tab
|
| asphalt pavement | TON | 1 | $66.12 | $66.12 to $66.12 | Bids- 2024-11-19 · Iowa DOT · 20-0352-471 · $66.12 per TON · qty 13603.75 · bid tab
|
| concrete pavement | EACH | 1 | $1.00 | $1.00 to $1.00 | Bids- 2024-03-19 · Iowa DOT · 20-0351-194 · $1.00 per EACH · qty 5221.0 · bid tab
|
| concrete pavement | SY | 2 | $97.00 | $94.00 to $100.00 | Bids- 2026-07-21 · Iowa DOT · 20-5772-607 · $100.00 per SY · qty 39.23 · bid tab
- 2024-03-19 · Iowa DOT · 20-0351-194 · $94.00 per SY · qty 4526.0 · bid tab
|
| curb gutter | EACH | 1 | $1.10 | $1.10 to $1.10 | Bids- 2026-07-21 · Iowa DOT · 20-5772-607 · $1.10 per EACH · qty 84.0 · bid tab
|
| curb gutter | LF | 4 | $59.99 | $15.00 to $73.01 | Bids- 2026-07-21 · Iowa DOT · 20-5772-607 · $64.33 per LF · qty 299.0 · bid tab
- 2026-07-21 · Iowa DOT · 20-5772-607 · $15.00 per LF · qty 84.0 · bid tab
- 2026-07-21 · Iowa DOT · 20-5772-607 · $55.65 per LF · qty 191.0 · bid tab
- 2026-07-21 · Iowa DOT · 20-5772-607 · $73.01 per LF · qty 104.0 · bid tab
|
| excavation embankment | CY | 7 | $12.50 | $6.29 to $35.00 | Bids- 2025-09-16 · Iowa DOT · 20-C020-126 · $14.00 per CY · qty 300.0 · bid tab
- 2025-09-16 · Iowa DOT · 20-C020-126 · $21.00 per CY · qty 673.0 · bid tab
- 2025-02-18 · Iowa DOT · 20-0692-033 · $6.29 per CY · qty 4371.7 · bid tab
- 2024-11-19 · Iowa DOT · 20-0352-471 · $35.00 per CY · qty 32.0 · bid tab
- 2024-08-20 · Iowa DOT · 20-5772-606 · $8.40 per CY · qty 295.0 · bid tab
- 2024-08-20 · Iowa DOT · 20-5772-606 · $12.50 per CY · qty 5625.0 · bid tab
- 2024-02-20 · Iowa DOT · 20-C020-123 · $7.45 per CY · qty 210.0 · bid tab
|
| lime cement stabilization | ACRE | 4 | $275.00 | $250.00 to $500.00 | Bids- 2025-09-16 · Iowa DOT · 20-C020-126 · $500.00 per ACRE · qty 0.7 · bid tab
- 2025-02-18 · Iowa DOT · 20-0692-033 · $250.00 per ACRE · qty 7.0 · bid tab
- 2024-08-20 · Iowa DOT · 20-5772-606 · $300.00 per ACRE · qty 3.0 · bid tab
- 2024-02-20 · Iowa DOT · 20-C020-123 · $250.00 per ACRE · qty 1.1 · bid tab
|
| lime cement stabilization | LF | 1 | $30.62 | $30.62 to $30.62 | Bids- 2024-03-19 · Iowa DOT · 20-0351-194 · $30.62 per LF · qty 200.0 · bid tab
|
| manhole | EACH | 2 | $1,830.00 | $1,760.00 to $1,900.00 | Bids- 2026-07-21 · Iowa DOT · 20-5772-607 · $1,760.00 per EACH · qty 5.0 · bid tab
- 2024-03-19 · Iowa DOT · 20-0351-194 · $1,900.00 per EACH · qty 1.0 · bid tab
|
| sidewalk | EACH | 2 | $3,150.00 | $2,800.00 to $3,500.00 | Bids- 2024-03-19 · Iowa DOT · 20-0351-194 · $3,500.00 per EACH · qty 1.0 · bid tab
- 2024-03-19 · Iowa DOT · 20-0351-194 · $2,800.00 per EACH · qty 1.0 · bid tab
|
| sidewalk | SY | 3 | $79.45 | $74.32 to $161.00 | Bids- 2026-07-21 · Iowa DOT · 20-5772-607 · $74.32 per SY · qty 569.52 · bid tab
- 2024-03-19 · Iowa DOT · 20-0351-194 · $79.45 per SY · qty 64.0 · bid tab
- 2024-03-19 · Iowa DOT · 20-0351-194 · $161.00 per SY · qty 8.0 · bid tab
|
| storm pipe 18-inch | LF | 2 | $77.00 | $55.00 to $99.00 | Bids- 2024-03-19 · Iowa DOT · 20-0351-194 · $99.00 per LF · qty 108.0 · bid tab
- 2024-02-20 · Iowa DOT · 20-C020-123 · $55.00 per LF · qty 40.0 · bid tab
|
| storm pipe 24-inch | LF | 1 | $119.00 | $119.00 to $119.00 | Bids- 2024-03-19 · Iowa DOT · 20-0351-194 · $119.00 per LF · qty 118.0 · bid tab
|
| storm pipe (diameter not stated) | LF | 1 | $26.50 | $26.50 to $26.50 | Bids- 2024-03-19 · Iowa DOT · 20-0351-194 · $26.50 per LF · qty 58.0 · bid tab
|