Site-work prices, St. Francis County, AR
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 7 | $131.30 | $120.00 to $158.04 | Bids- 2025-04-09 · ARDOT · A10044 · $128.57 per TON · qty 282.0 · bid tab
- 2025-04-09 · ARDOT · A10044 · $131.30 per TON · qty 42.0 · bid tab
- 2025-02-26 · ARDOT · A10045 · $120.00 per TON · qty 1747.0 · bid tab
- 2025-02-26 · ARDOT · A10045 · $120.00 per TON · qty 312.0 · bid tab
- 2024-11-06 · ARDOT · 110717 · $158.00 per TON · qty 62.0 · bid tab
- 2024-11-06 · ARDOT · 110717 · $158.00 per TON · qty 83.0 · bid tab
- 2024-02-28 · ARDOT · SA6868 · $158.04 per TON · qty 186.0 · bid tab
|
| excavation embankment | CUYD | 2 | $30.30 | $22.80 to $37.80 | Bids- 2024-11-06 · ARDOT · 110717 · $22.80 per CUYD · qty 5253.0 · bid tab
- 2024-11-06 · ARDOT · 110717 · $37.80 per CUYD · qty 17364.0 · bid tab
|
| flexible base | TON | 4 | $66.72 | $43.10 to $110.70 | Bids- 2025-04-09 · ARDOT · A10044 · $73.50 per TON · qty 263.0 · bid tab
- 2025-02-26 · ARDOT · A10045 · $59.95 per TON · qty 1873.0 · bid tab
- 2024-11-06 · ARDOT · 110717 · $43.10 per TON · qty 4162.0 · bid tab
- 2024-02-28 · ARDOT · SA6868 · $110.70 per TON · qty 155.0 · bid tab
|
| lime cement stabilization | TON | 2 | $226.00 | $107.00 to $345.00 | Bids- 2024-11-06 · ARDOT · 110717 · $107.00 per TON · qty 8.0 · bid tab
- 2024-11-06 · ARDOT · 110717 · $345.00 per TON · qty 250.0 · bid tab
|
| storm pipe 48-inch | LF | 1 | $406.00 | $406.00 to $406.00 | Bids- 2024-11-06 · ARDOT · 110717 · $406.00 per LF · qty 32.0 · bid tab
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.