| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 13 | $120.00 | $113.83 to $680.00 | Bids- 2026-03-04 · ARDOT · A90038 · $120.00 per TON · qty 2051.0 · bid tab
- 2026-03-04 · ARDOT · A90038 · $120.00 per TON · qty 269.0 · bid tab
- 2026-03-04 · ARDOT · A90038 · $113.83 per TON · qty 108.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $120.00 per TON · qty 35.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $120.00 per TON · qty 76.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $425.00 per TON · qty 30.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $120.00 per TON · qty 10.0 · bid tab
- 2025-11-05 · ARDOT · A90041 · $120.00 per TON · qty 18.0 · bid tab
- 2025-11-05 · ARDOT · A90041 · $120.00 per TON · qty 1201.0 · bid tab
- 2025-05-21 · ARDOT · SA6447 · $120.00 per TON · qty 135.0 · bid tab
(10 most recent of 13 shown; all in the Hubstake feed) |
| curb gutter | LF | 1 | $30.00 | $30.00 to $30.00 | Bids- 2025-11-05 · ARDOT · 090672 · $30.00 per LF · qty 2926.0 · bid tab
|
| excavation embankment | CUYD | 4 | $34.80 | $18.00 to $48.39 | Bids- 2026-03-04 · ARDOT · A90038 · $48.39 per CUYD · qty 15.0 · bid tab
- 2026-03-04 · ARDOT · A90038 · $34.59 per CUYD · qty 270.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $18.00 per CUYD · qty 11267.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $35.00 per CUYD · qty 1242.0 · bid tab
|
| fire hydrant | EACH | 1 | $2,500.00 | $2,500.00 to $2,500.00 | Bids- 2025-11-05 · ARDOT · 090672 · $2,500.00 per EACH · qty 1.0 · bid tab
|
| flexible base | STA | 1 | $124.44 | $124.44 to $124.44 | Bids- 2025-05-21 · ARDOT · SA6447 · $124.44 per STA · qty 94.0 · bid tab
|
| flexible base | TON | 4 | $29.00 | $24.92 to $55.81 | Bids- 2026-03-04 · ARDOT · A90038 · $24.92 per TON · qty 2505.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $30.00 per TON · qty 2307.0 · bid tab
- 2025-11-05 · ARDOT · A90041 · $28.00 per TON · qty 500.0 · bid tab
- 2024-02-28 · ARDOT · C64006 · $55.81 per TON · qty 621.0 · bid tab
|
| inlet headwall | EACH | 2 | $2,000.00 | $1,500.00 to $2,500.00 | Bids- 2025-11-05 · ARDOT · 090672 · $2,500.00 per EACH · qty 2.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $1,500.00 per EACH · qty 15.0 · bid tab
|
| lime cement stabilization | TON | 3 | $95.00 | $5.00 to $95.00 | Bids- 2026-03-04 · ARDOT · A90038 · $95.00 per TON · qty 10.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $95.00 per TON · qty 2.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $5.00 per TON · qty 100.0 · bid tab
|
| manhole | EACH | 2 | $6,250.00 | $4,000.00 to $8,500.00 | Bids- 2025-11-05 · ARDOT · 090672 · $4,000.00 per EACH · qty 8.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $8,500.00 per EACH · qty 7.0 · bid tab
|
| sewer main 8-inch | LF | 1 | $78.00 | $78.00 to $78.00 | Bids- 2025-11-05 · ARDOT · 090672 · $78.00 per LF · qty 520.0 · bid tab
|
| sewer service | LF | 1 | $32.00 | $32.00 to $32.00 | Bids- 2025-11-05 · ARDOT · 090672 · $32.00 per LF · qty 340.0 · bid tab
|
| storm pipe 24-inch | LF | 2 | $118.00 | $108.92 to $127.07 | Bids- 2026-03-04 · ARDOT · A90038 · $108.92 per LF · qty 55.0 · bid tab
- 2026-03-04 · ARDOT · A90038 · $127.07 per LF · qty 200.0 · bid tab
|
| storm pipe 36-inch | LF | 1 | $318.96 | $318.96 to $318.96 | Bids- 2026-03-04 · ARDOT · A90038 · $318.96 per LF · qty 40.0 · bid tab
|
| storm pipe 48-inch | LF | 1 | $443.33 | $443.33 to $443.33 | Bids- 2026-03-04 · ARDOT · A90038 · $443.33 per LF · qty 40.0 · bid tab
|
| storm pipe 59-inch | LF | 2 | $375.00 | $375.00 to $375.00 | Bids- 2025-11-05 · ARDOT · 090672 · $375.00 per LF · qty 120.0 · bid tab
- 2025-11-05 · ARDOT · 090672 · $375.00 per LF · qty 142.0 · bid tab
|
| water main 2-inch | LF | 1 | $28.00 | $28.00 to $28.00 | Bids- 2025-11-05 · ARDOT · 090672 · $28.00 per LF · qty 280.0 · bid tab
|