Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON6$120.00$120.00 to $600.00
Bids
  • 2025-04-09 · ARDOT · SA6258 · $120.00 per TON · qty 108.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $120.00 per TON · qty 846.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $120.00 per TON · qty 7.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $120.00 per TON · qty 9.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $600.00 per TON · qty 139.0 · bid tab
  • 2025-01-15 · ARDOT · A60042 · $120.00 per TON · qty 1321.0 · bid tab
concrete pavementSQYD4$120.00$13.14 to $165.00
Bids
  • 2025-02-26 · ARDOT · 061708 · $120.00 per SQYD · qty 167.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $165.00 per SQYD · qty 2217.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $120.00 per SQYD · qty 5819.0 · bid tab
  • 2025-01-15 · ARDOT · A60042 · $13.14 per SQYD · qty 1516.0 · bid tab
curb gutterLF2$31.27$28.53 to $34.00
Bids
  • 2025-02-26 · ARDOT · 061708 · $34.00 per LF · qty 13656.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $28.53 per LF · qty 2262.0 · bid tab
excavation embankmentCUYD2$55.05$54.19 to $55.92
Bids
  • 2025-02-26 · ARDOT · 061708 · $55.92 per CUYD · qty 16232.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $54.19 per CUYD · qty 11102.0 · bid tab
flexible baseTON1$46.70$46.70 to $46.70
Bids
  • 2025-02-26 · ARDOT · 061708 · $46.70 per TON · qty 23121.0 · bid tab
inlet headwallEACH2$2,677.19$2,131.60 to $3,222.78
Bids
  • 2025-02-26 · ARDOT · 061708 · $3,222.78 per EACH · qty 8.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $2,131.60 per EACH · qty 44.0 · bid tab
lime cement stabilizationSQYD1$2.75$2.75 to $2.75
Bids
  • 2025-02-26 · ARDOT · 061708 · $2.75 per SQYD · qty 2621.0 · bid tab
lime cement stabilizationTON4$143.88$100.00 to $637.48
Bids
  • 2025-02-26 · ARDOT · 061708 · $143.81 per TON · qty 862.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $637.48 per TON · qty 100.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $143.94 per TON · qty 55.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $100.00 per TON · qty 10.0 · bid tab
manholeEACH2$7,295.59$6,398.46 to $8,192.72
Bids
  • 2025-02-26 · ARDOT · 061708 · $8,192.72 per EACH · qty 7.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $6,398.46 per EACH · qty 1.0 · bid tab
storm pipe 18-inchLF3$95.35$85.07 to $104.67
Bids
  • 2025-02-26 · ARDOT · 061708 · $85.07 per LF · qty 265.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $104.67 per LF · qty 2324.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $95.35 per LF · qty 3013.0 · bid tab
storm pipe 24-inchLF2$192.62$139.90 to $245.33
Bids
  • 2025-02-26 · ARDOT · 061708 · $139.90 per LF · qty 801.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $245.33 per LF · qty 133.0 · bid tab
storm pipe 30-inchLF2$352.14$171.14 to $533.14
Bids
  • 2025-02-26 · ARDOT · 061708 · $171.14 per LF · qty 1111.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $533.14 per LF · qty 128.0 · bid tab
storm pipe 36-inchLF2$376.69$262.35 to $491.03
Bids
  • 2025-02-26 · ARDOT · 061708 · $491.03 per LF · qty 96.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $262.35 per LF · qty 294.0 · bid tab
storm pipe 42-inchLF1$507.70$507.70 to $507.70
Bids
  • 2025-02-26 · ARDOT · 061708 · $507.70 per LF · qty 10.0 · bid tab
storm pipe 48-inchLF2$1,579.10$1,561.20 to $1,596.99
Bids
  • 2025-02-26 · ARDOT · 061708 · $1,561.20 per LF · qty 8.0 · bid tab
  • 2025-02-26 · ARDOT · 061708 · $1,596.99 per LF · qty 40.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.