Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON13$120.00$120.00 to $1,200.00
Bids
  • 2026-03-04 · ARDOT · 101003 · $120.00 per TON · qty 44.0 · bid tab
  • 2026-03-04 · ARDOT · 101003 · $120.00 per TON · qty 97.0 · bid tab
  • 2026-03-04 · ARDOT · 101003 · $350.00 per TON · qty 9.0 · bid tab
  • 2026-01-21 · ARDOT · SA6146 · $120.00 per TON · qty 148.0 · bid tab
  • 2025-11-05 · ARDOT · A00094 · $1,200.00 per TON · qty 272.0 · bid tab
  • 2025-11-05 · ARDOT · A00094 · $1,200.00 per TON · qty 1687.0 · bid tab
  • 2025-02-26 · ARDOT · 101234 · $120.00 per TON · qty 124.0 · bid tab
  • 2025-02-26 · ARDOT · 101234 · $120.00 per TON · qty 38.0 · bid tab
  • 2025-02-26 · ARDOT · 101234 · $120.00 per TON · qty 25.0 · bid tab
  • 2025-02-26 · ARDOT · A00085 · $120.00 per TON · qty 1005.0 · bid tab
(10 most recent of 13 shown; all in the Hubstake feed)
curb gutterLF1$40.00$40.00 to $40.00
Bids
  • 2025-11-05 · ARDOT · A00094 · $40.00 per LF · qty 40.0 · bid tab
excavation embankmentCUYD5$18.04$15.09 to $42.00
Bids
  • 2026-04-08 · ARDOT · 101115 · $15.09 per CUYD · qty 11799.0 · bid tab
  • 2026-03-04 · ARDOT · 101003 · $20.50 per CUYD · qty 27187.0 · bid tab
  • 2026-03-04 · ARDOT · 101003 · $16.00 per CUYD · qty 5901.0 · bid tab
  • 2025-11-05 · ARDOT · A00094 · $42.00 per CUYD · qty 400.0 · bid tab
  • 2025-02-26 · ARDOT · 101234 · $18.04 per CUYD · qty 1695.0 · bid tab
flexible baseSQYD1$8.48$8.48 to $8.48
Bids
  • 2025-02-26 · ARDOT · A00085 · $8.48 per SQYD · qty 80738.0 · bid tab
flexible baseTON11$32.00$26.79 to $233.91
Bids
  • 2026-04-08 · ARDOT · 101115 · $67.06 per TON · qty 235.0 · bid tab
  • 2026-03-04 · ARDOT · 101003 · $32.00 per TON · qty 5637.0 · bid tab
  • 2026-01-21 · ARDOT · SA6146 · $26.79 per TON · qty 308.0 · bid tab
  • 2025-11-05 · ARDOT · A00094 · $28.00 per TON · qty 2627.0 · bid tab
  • 2025-02-26 · ARDOT · 101234 · $28.35 per TON · qty 897.0 · bid tab
  • 2025-02-26 · ARDOT · 101234 · $86.39 per TON · qty 984.0 · bid tab
  • 2025-02-26 · ARDOT · A00085 · $233.91 per TON · qty 3589.0 · bid tab
  • 2025-02-26 · ARDOT · A00085 · $26.84 per TON · qty 1167.0 · bid tab
  • 2025-02-26 · ARDOT · A00085 · $33.39 per TON · qty 292.0 · bid tab
  • 2025-02-26 · ARDOT · SA6145 · $27.44 per TON · qty 380.0 · bid tab
(10 most recent of 11 shown; all in the Hubstake feed)
lime cement stabilizationTON3$75.00$20.00 to $150.00
Bids
  • 2026-04-08 · ARDOT · 101115 · $20.00 per TON · qty 12.0 · bid tab
  • 2026-03-04 · ARDOT · 101003 · $75.00 per TON · qty 18.0 · bid tab
  • 2026-03-04 · ARDOT · 101003 · $150.00 per TON · qty 50.0 · bid tab
storm pipe 24-inchLF2$112.50$95.00 to $130.00
Bids
  • 2026-03-04 · ARDOT · 101003 · $130.00 per LF · qty 83.0 · bid tab
  • 2025-11-05 · ARDOT · A00094 · $95.00 per LF · qty 196.0 · bid tab
storm pipe 36-inchLF2$130.00$120.00 to $140.00
Bids
  • 2025-11-05 · ARDOT · A00094 · $140.00 per LF · qty 120.0 · bid tab
  • 2025-11-05 · ARDOT · A00094 · $120.00 per LF · qty 64.0 · bid tab
storm pipe 42-inchLF1$220.00$220.00 to $220.00
Bids
  • 2025-11-05 · ARDOT · A00094 · $220.00 per LF · qty 282.0 · bid tab
storm pipe 48-inchLF1$230.00$230.00 to $230.00
Bids
  • 2025-11-05 · ARDOT · A00094 · $230.00 per LF · qty 144.0 · bid tab
storm pipe 60-inchLF1$435.00$435.00 to $435.00
Bids
  • 2025-11-05 · ARDOT · A00094 · $435.00 per LF · qty 158.0 · bid tab
storm pipe 66-inchLF1$500.00$500.00 to $500.00
Bids
  • 2025-11-05 · ARDOT · A00094 · $500.00 per LF · qty 208.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.