Site-work prices, Nevada, Pike County, AR
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | TON | 1 | $120.00 | $120.00 to $120.00 | Bids
|
| excavation embankment | CUYD | 1 | $82.29 | $82.29 to $82.29 | Bids
|
| flexible base | TON | 1 | $60.71 | $60.71 to $60.71 | Bids
|
| lime cement stabilization | TON | 1 | $125.00 | $125.00 to $125.00 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.