PadstakeGet the fee reports
Menu

Site-work prices, Hot Spring County, AR

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON9$301.24$83.00 to $1,418.00
Bids
  • 2026-06-24 · ARDOT · SA3056 · $825.00 per TON · qty 251.0 · bid tab
  • 2026-05-20 · ARDOT · A60058 · $1,418.00 per TON · qty 1160.0 · bid tab
  • 2025-04-09 · ARDOT · SA3055 · $120.00 per TON · qty 103.0 · bid tab
  • 2025-04-09 · ARDOT · SA3055 · $83.00 per TON · qty 950.0 · bid tab
  • 2025-02-26 · ARDOT · A60035 · $120.00 per TON · qty 488.0 · bid tab
  • 2024-09-18 · ARDOT · 061741 · $388.87 per TON · qty 32.0 · bid tab
  • 2024-09-18 · ARDOT · 061741 · $301.24 per TON · qty 81.0 · bid tab
  • 2024-09-18 · ARDOT · 061741 · $388.87 per TON · qty 28.0 · bid tab
  • 2024-09-18 · ARDOT · 061741 · $301.24 per TON · qty 53.0 · bid tab
excavation embankmentCUYD2$27.00$22.00 to $32.00
Bids
  • 2024-09-18 · ARDOT · 061741 · $32.00 per CUYD · qty 5962.0 · bid tab
  • 2024-09-18 · ARDOT · 061741 · $22.00 per CUYD · qty 12698.0 · bid tab
flexible baseTON3$47.96$40.45 to $58.17
Bids
  • 2026-05-20 · ARDOT · A60058 · $47.96 per TON · qty 728.0 · bid tab
  • 2025-02-26 · ARDOT · A60035 · $58.17 per TON · qty 355.0 · bid tab
  • 2024-09-18 · ARDOT · 061741 · $40.45 per TON · qty 6536.0 · bid tab
lime cement stabilizationTON3$359.14$118.30 to $500.00
Bids
  • 2025-02-26 · ARDOT · A60035 · $500.00 per TON · qty 2.0 · bid tab
  • 2024-09-18 · ARDOT · 061741 · $118.30 per TON · qty 22.0 · bid tab
  • 2024-09-18 · ARDOT · 061741 · $359.14 per TON · qty 200.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.