Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | TON | 2 | $120.00 | $120.00 to $120.00 | |
| flexible base | STA | 1 | $1,500.00 | $1,500.00 to $1,500.00 | Bids
|
| flexible base | TON | 1 | $34.50 | $34.50 to $34.50 | Bids
|
| lime cement stabilization | TON | 1 | $500.00 | $500.00 to $500.00 | Bids
|
| storm pipe 24-inch | LF | 1 | $425.00 | $425.00 to $425.00 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.