Site-work prices, Carroll County, AR
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 9 | $120.00 | $120.00 to $120.00 | Bids- 2026-04-08 · ARDOT · A90040 · $120.00 per TON · qty 2600.0 · bid tab
- 2026-03-04 · ARDOT · 090593 · $120.00 per TON · qty 12.0 · bid tab
- 2026-03-04 · ARDOT · C08012 · $120.00 per TON · qty 183.0 · bid tab
- 2025-04-09 · ARDOT · A90034 · $120.00 per TON · qty 610.0 · bid tab
- 2025-04-09 · ARDOT · A90034 · $120.00 per TON · qty 1733.0 · bid tab
- 2025-01-15 · ARDOT · SA0859 · $120.00 per TON · qty 250.0 · bid tab
- 2024-11-06 · ARDOT · A90026 · $120.00 per TON · qty 1399.0 · bid tab
- 2024-11-06 · ARDOT · A90026 · $120.00 per TON · qty 52.0 · bid tab
- 2024-01-17 · ARDOT · C08011 · $120.00 per TON · qty 71.0 · bid tab
|
| curb gutter | LF | 1 | $90.00 | $90.00 to $90.00 | Bids- 2026-03-04 · ARDOT · 090593 · $90.00 per LF · qty 314.0 · bid tab
|
| excavation embankment | CUYD | 2 | $250.00 | $200.00 to $300.00 | Bids- 2026-03-04 · ARDOT · 090593 · $300.00 per CUYD · qty 4.0 · bid tab
- 2026-03-04 · ARDOT · 090593 · $200.00 per CUYD · qty 44.0 · bid tab
|
| flexible base | TON | 3 | $39.29 | $32.30 to $45.48 | Bids- 2026-04-08 · ARDOT · A90040 · $45.48 per TON · qty 1360.0 · bid tab
- 2025-04-09 · ARDOT · A90034 · $32.30 per TON · qty 736.0 · bid tab
- 2024-11-06 · ARDOT · A90026 · $39.29 per TON · qty 2077.0 · bid tab
|
| lime cement stabilization | TON | 2 | $82.32 | $1.00 to $163.64 | Bids- 2026-03-04 · ARDOT · 090593 · $1.00 per TON · qty 5.0 · bid tab
- 2024-11-06 · ARDOT · A90026 · $163.64 per TON · qty 2.0 · bid tab
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.