Site-work prices, Morgan County, AL

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTon51$95.08$63.00 to $230.00
Bids
  • 2026-08-28 · ALDOT · 20260828030 · $152.00 per Ton · qty 100.0 · bid tab
  • 2026-08-28 · ALDOT · 20260828030 · $175.00 per Ton · qty 100.0 · bid tab
  • 2026-08-28 · ALDOT · 20260828030 · $175.00 per Ton · qty 100.0 · bid tab
  • 2026-08-28 · ALDOT · 20260828030 · $193.00 per Ton · qty 75.0 · bid tab
  • 2026-08-28 · ALDOT · 20260828030 · $150.00 per Ton · qty 142.0 · bid tab
  • 2026-08-28 · ALDOT · 20260828030 · $130.00 per Ton · qty 396.0 · bid tab
  • 2026-08-28 · ALDOT · 20260828030 · $230.00 per Ton · qty 20.0 · bid tab
  • 2026-04-24 · ALDOT · 20260424012 · $74.00 per Ton · qty 1263.0 · bid tab
  • 2026-04-24 · ALDOT · 20260424012 · $96.00 per Ton · qty 684.0 · bid tab
  • 2026-04-24 · ALDOT · 20260424012 · $74.00 per Ton · qty 5791.0 · bid tab
(10 most recent of 51 shown; all in the Hubstake feed)
concrete pavementCUYD1$1,241.38$1,241.38 to $1,241.38
Bids
  • 2025-12-05 · ALDOT · 20251205055 · $1,241.38 per CUYD · qty 307.0 · bid tab
concrete pavementLF2$2.73$2.17 to $3.29
Bids
  • 2025-12-05 · ALDOT · 20251205055 · $2.17 per LF · qty 32421.0 · bid tab
  • 2025-12-05 · ALDOT · 20251205055 · $3.29 per LF · qty 1214.0 · bid tab
concrete pavementSQYD1$5.28$5.28 to $5.28
Bids
  • 2025-12-05 · ALDOT · 20251205055 · $5.28 per SQYD · qty 48719.0 · bid tab
curb gutterLF4$31.50$27.00 to $90.00
Bids
  • 2026-08-28 · ALDOT · 20260828030 · $90.00 per LF · qty 250.0 · bid tab
  • 2026-08-28 · ALDOT · 20260828030 · $34.00 per LF · qty 1050.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $29.00 per LF · qty 74.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $27.00 per LF · qty 1320.0 · bid tab
excavation embankmentCUYD9$23.00$18.50 to $40.00
Bids
  • 2026-08-28 · ALDOT · 20260828030 · $18.50 per CUYD · qty 1649.0 · bid tab
  • 2026-08-28 · ALDOT · 20260828030 · $38.50 per CUYD · qty 489.0 · bid tab
  • 2026-04-24 · ALDOT · 20260424041 · $22.16 per CUYD · qty 3376.0 · bid tab
  • 2025-07-25 · ALDOT · 20250725024 · $18.50 per CUYD · qty 5914.0 · bid tab
  • 2025-07-25 · ALDOT · 20250725024 · $25.50 per CUYD · qty 4929.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $20.50 per CUYD · qty 1675.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $40.00 per CUYD · qty 2149.0 · bid tab
  • 2025-03-28 · ALDOT · 20250328038 · $34.00 per CUYD · qty 1458.0 · bid tab
  • 2025-03-28 · ALDOT · 20250328038 · $23.00 per CUYD · qty 2755.0 · bid tab
flexible baseSQYD4$15.00$10.50 to $17.00
Bids
  • 2026-08-28 · ALDOT · 20260828030 · $17.00 per SQYD · qty 2258.0 · bid tab
  • 2025-07-25 · ALDOT · 20250725024 · $10.50 per SQYD · qty 5600.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $17.00 per SQYD · qty 331.0 · bid tab
  • 2025-03-28 · ALDOT · 20250328038 · $13.00 per SQYD · qty 1958.0 · bid tab
flexible baseTon9$32.27$28.00 to $56.08
Bids
  • 2026-04-24 · ALDOT · 20260424012 · $32.27 per Ton · qty 318.0 · bid tab
  • 2026-04-24 · ALDOT · 20260424041 · $30.00 per Ton · qty 400.0 · bid tab
  • 2026-03-27 · ALDOT · 20260327011 · $36.56 per Ton · qty 835.0 · bid tab
  • 2026-01-30 · ALDOT · 20260130026 · $30.57 per Ton · qty 689.0 · bid tab
  • 2025-12-05 · ALDOT · 20251205055 · $56.08 per Ton · qty 1480.0 · bid tab
  • 2025-02-28 · ALDOT · 20250228015 · $41.52 per Ton · qty 304.0 · bid tab
  • 2025-01-31 · ALDOT · 20250131026 · $36.75 per Ton · qty 240.0 · bid tab
  • 2024-02-23 · ALDOT · 20240223035 · $28.00 per Ton · qty 993.0 · bid tab
  • 2023-12-08 · ALDOT · 20231208024 · $29.67 per Ton · qty 812.0 · bid tab
lime cement stabilizationSQYD1$3.00$3.00 to $3.00
Bids
  • 2026-04-24 · ALDOT · 20260424041 · $3.00 per SQYD · qty 1500.0 · bid tab
manholeEach6$4,525.00$450.00 to $4,850.00
Bids
  • 2026-08-28 · ALDOT · 20260828030 · $450.00 per Each · qty 2.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $4,850.00 per Each · qty 1.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $4,850.00 per Each · qty 2.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $3,000.00 per Each · qty 2.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $4,850.00 per Each · qty 2.0 · bid tab
  • 2025-03-28 · ALDOT · 20250328038 · $4,200.00 per Each · qty 2.0 · bid tab
storm pipe 12-inchLF1$310.00$310.00 to $310.00
Bids
  • 2025-03-28 · ALDOT · 20250328038 · $310.00 per LF · qty 42.0 · bid tab
storm pipe 15-inchLF2$82.50$77.00 to $88.00
Bids
  • 2026-08-28 · ALDOT · 20260828030 · $77.00 per LF · qty 34.0 · bid tab
  • 2026-08-28 · ALDOT · 20260828030 · $88.00 per LF · qty 76.0 · bid tab
storm pipe 18-inchLF5$80.00$72.00 to $215.00
Bids
  • 2026-08-28 · ALDOT · 20260828030 · $80.00 per LF · qty 189.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $75.00 per LF · qty 328.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $182.00 per LF · qty 6.0 · bid tab
  • 2025-03-28 · ALDOT · 20250328038 · $72.00 per LF · qty 555.0 · bid tab
  • 2025-03-28 · ALDOT · 20250328038 · $215.00 per LF · qty 11.0 · bid tab
storm pipe 22-inchLF2$102.50$100.00 to $105.00
Bids
  • 2025-05-30 · ALDOT · 20250530034 · $100.00 per LF · qty 226.0 · bid tab
  • 2025-03-28 · ALDOT · 20250328038 · $105.00 per LF · qty 57.0 · bid tab
storm pipe 24-inchLF1$90.00$90.00 to $90.00
Bids
  • 2025-03-28 · ALDOT · 20250328038 · $90.00 per LF · qty 203.0 · bid tab
storm pipe 29-inchLF1$117.00$117.00 to $117.00
Bids
  • 2025-05-30 · ALDOT · 20250530034 · $117.00 per LF · qty 56.0 · bid tab
storm pipe 44-inchLF2$253.00$196.00 to $310.00
Bids
  • 2025-05-30 · ALDOT · 20250530034 · $310.00 per LF · qty 11.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $196.00 per LF · qty 50.0 · bid tab
water main 6-inchLF1$48.00$48.00 to $48.00
Bids
  • 2025-05-30 · ALDOT · 20250530034 · $48.00 per LF · qty 180.0 · bid tab
water main 8-inchLF1$90.00$90.00 to $90.00
Bids
  • 2025-05-30 · ALDOT · 20250530034 · $90.00 per LF · qty 620.0 · bid tab
water serviceLF2$38.25$35.50 to $41.00
Bids
  • 2025-05-30 · ALDOT · 20250530034 · $41.00 per LF · qty 130.0 · bid tab
  • 2025-05-30 · ALDOT · 20250530034 · $35.50 per LF · qty 100.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.