Site-work prices, Mobile, Baldwin County, AL
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | Ton | 7 | $148.08 | $130.85 to $164.12 | Bids
|
| curb gutter | LF | 1 | $56.51 | $56.51 to $56.51 | Bids
|
| excavation embankment | CUYD | 3 | $24.14 | $2.46 to $31.11 | |
| fire hydrant | Each | 1 | $11,303.78 | $11,303.78 to $11,303.78 | Bids
|
| flexible base | SQYD | 1 | $45.59 | $45.59 to $45.59 | Bids
|
| flexible base | Ton | 1 | $112.21 | $112.21 to $112.21 | Bids
|
| manhole | Each | 1 | $6,616.84 | $6,616.84 to $6,616.84 | Bids
|
| storm pipe 22-inch | LF | 2 | $197.38 | $191.58 to $203.18 | |
| storm pipe 24-inch | LF | 1 | $163.18 | $163.18 to $163.18 | Bids
|
| storm pipe 30-inch | LF | 1 | $182.76 | $182.76 to $182.76 | Bids
|
| storm pipe 48-inch | LF | 1 | $137.85 | $137.85 to $137.85 | Bids
|
| water main 10-inch | LF | 1 | $170.93 | $170.93 to $170.93 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.