Site-work prices, Blount County, AL

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTon23$115.47$69.24 to $413.94
Bids
  • 2026-06-26 · ALDOT · 20260626020 · $109.54 per Ton · qty 15775.0 · bid tab
  • 2026-06-26 · ALDOT · 20260626020 · $118.20 per Ton · qty 200.0 · bid tab
  • 2026-06-26 · ALDOT · 20260626020 · $192.39 per Ton · qty 305.0 · bid tab
  • 2026-03-27 · ALDOT · 20260327014 · $145.11 per Ton · qty 445.0 · bid tab
  • 2026-03-27 · ALDOT · 20260327014 · $85.37 per Ton · qty 750.0 · bid tab
  • 2026-03-27 · ALDOT · 20260327014 · $90.06 per Ton · qty 11375.0 · bid tab
  • 2025-06-27 · ALDOT · 20250627001 · $132.90 per Ton · qty 719.0 · bid tab
  • 2025-06-27 · ALDOT · 20250627001 · $261.44 per Ton · qty 28.0 · bid tab
  • 2025-06-27 · ALDOT · 20250627001 · $163.40 per Ton · qty 62.0 · bid tab
  • 2025-06-27 · ALDOT · 20250627001 · $138.34 per Ton · qty 763.0 · bid tab
(10 most recent of 23 shown; all in the Hubstake feed)
excavation embankmentCUYD6$29.67$2.60 to $71.00
Bids
  • 2025-06-27 · ALDOT · 20250627001 · $29.67 per CUYD · qty 17230.0 · bid tab
  • 2025-06-27 · ALDOT · 20250627001 · $29.67 per CUYD · qty 6375.0 · bid tab
  • 2025-01-31 · ALDOT · 20250131022 · $35.00 per CUYD · qty 120.0 · bid tab
  • 2025-01-31 · ALDOT · 20250131022 · $71.00 per CUYD · qty 75.0 · bid tab
  • 2024-01-26 · ALDOT · 20240126001 · $13.87 per CUYD · qty 70986.0 · bid tab
  • 2024-01-26 · ALDOT · 20240126001 · $2.60 per CUYD · qty 71139.0 · bid tab
flexible baseSQYD2$14.36$9.48 to $19.24
Bids
  • 2025-06-27 · ALDOT · 20250627001 · $19.24 per SQYD · qty 5955.0 · bid tab
  • 2024-01-26 · ALDOT · 20240126001 · $9.48 per SQYD · qty 10235.0 · bid tab
inlet headwallEach1$1,074.12$1,074.12 to $1,074.12
Bids
  • 2024-01-26 · ALDOT · 20240126001 · $1,074.12 per Each · qty 1.0 · bid tab
lime cement stabilizationSQYD1$5.12$5.12 to $5.12
Bids
  • 2025-06-27 · ALDOT · 20250627001 · $5.12 per SQYD · qty 1495.0 · bid tab
manholeEach3$8,055.84$1,500.25 to $15,250.49
Bids
  • 2025-06-27 · ALDOT · 20250627001 · $15,250.49 per Each · qty 1.0 · bid tab
  • 2024-01-26 · ALDOT · 20240126001 · $8,055.84 per Each · qty 5.0 · bid tab
  • 2024-01-26 · ALDOT · 20240126001 · $1,500.25 per Each · qty 6.0 · bid tab
storm pipe 15-inchLF1$81.84$81.84 to $81.84
Bids
  • 2024-01-26 · ALDOT · 20240126001 · $81.84 per LF · qty 33.0 · bid tab
storm pipe 18-inchLF2$171.23$95.83 to $246.64
Bids
  • 2024-01-26 · ALDOT · 20240126001 · $246.64 per LF · qty 4.0 · bid tab
  • 2024-01-26 · ALDOT · 20240126001 · $95.83 per LF · qty 37.0 · bid tab
storm pipe 24-inchLF4$103.52$101.16 to $157.27
Bids
  • 2025-06-27 · ALDOT · 20250627001 · $102.32 per LF · qty 36.0 · bid tab
  • 2024-01-26 · ALDOT · 20240126001 · $157.27 per LF · qty 8.0 · bid tab
  • 2024-01-26 · ALDOT · 20240126001 · $101.16 per LF · qty 44.0 · bid tab
  • 2024-01-26 · ALDOT · 20240126001 · $104.72 per LF · qty 116.0 · bid tab
storm pipe 42-inchLF2$217.75$189.93 to $245.56
Bids
  • 2025-06-27 · ALDOT · 20250627001 · $245.56 per LF · qty 70.0 · bid tab
  • 2024-01-26 · ALDOT · 20240126001 · $189.93 per LF · qty 24.0 · bid tab
storm pipe (diameter not stated)LF2$165.00$100.00 to $230.00
Bids
  • 2026-03-27 · ALDOT · 20260327014 · $100.00 per LF · qty 25.0 · bid tab
  • 2024-06-28 · ALDOT · 20240628017 · $230.00 per LF · qty 100.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.