Padstake
Menu

Seattle, WA

Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

$17,433listed total
Nonerank by 2025 new single-family permits

Not included: Included: Seattle SDCI building permit fee and plan review fee (each 100% of the Development Fee Index from Table D-1, on the Padstake standard valuation) and the Seattle Public Utilities water and wastewater system development charges for a 3/4-inch meter (effective 1/1/2026). Seattle charges no parks, schools or transportation impact fees. Not included: drainage SDC $1,225 per 1,000 sq ft of new hard surface (depends on the site), water tap/service installation (the SPU Development Services Office menu lists about $4,800-$6,175 for a 3/4-inch service, not stored), side sewer permit, mechanical/electrical/plumbing permits, minimum fees, school and other district fees. Searched 2026-11-09.

Water/sewer provider: City of Seattle SDCI (permits); Seattle Public Utilities (water, sewer)

LinePrinted ratePrototypeReceipt
Building permit fee (100% of Development Fee Index)
permit · computed
$2,984 for the first $250,000 of value plus $7.50 for each additional $1,000 of value or fraction thereof (Development Fee Index)
percent of valuation
$3,966.50Valuation $380,268 (ICC BVD R-3 V-B 175.92 x 2,000 + U V-B 71.07 x 400); 131 additional $1,000 units x 7.50 + 2,984 = 3,966.50; permit fee 100% of DFI
Effective 2026-01-01
Source · City of Seattle SDCI 2026 Fee Subtitle, Table D-1 / D-2 (22.900D.010)
fetched 2026-11-09, sha256 d7c6bc15590c
Building plan review fee (100% of Development Fee Index)
permit · computed
100% of DFI
percent of DFI
$3,966.50100% x 3,966.50
Effective 2026-01-01
Source · City of Seattle SDCI 2026 Fee Subtitle, Table D-1 / D-2 (22.900D.010)
fetched 2026-11-09, sha256 d7c6bc15590c
SPU water system development charge, 3/4-inch meter
water
$6,900
per meter
$6,900Printed
Effective 2026-01-01
Source · Seattle Public Utilities System Development Charge, revised 1/1/2026, 0.75-inch meter
fetched 2026-11-09, sha256 35785c5586b7
SPU wastewater system development charge, 3/4-inch meter
sewer
$2,600
per meter
$2,600Printed
Effective 2026-01-01
Source · Seattle Public Utilities System Development Charge, revised 1/1/2026, 0.75-inch meter
fetched 2026-11-09, sha256 35785c5586b7
Total listed$17,433

Fee-change calendar

Need the full report for a parcel?

The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199

Delivered as a web page and PDF within 1 business day.

Watch this jurisdiction

Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.