Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.
Not included: Full set from Bothell 2026 documents: fire, school, park/open space and transportation impact fees (with 3% traffic administrative fee), water facility charge, sewer facility charge (one RCE), storm drainage charge (one 2,000 sf impervious unit assumed), side sewer connection, building permit, plan check, residential site review and state fee. Not included: 5% development technology surcharge, mechanical and plumbing permits (separate application), water meter charge and main line taps, fire plan check, planning review fee ($231), Northshore school fee beyond the printed $16,550. Searched 2026-11-09.
Water/sewer provider: City of Bothell (water, sewer, stormwater)
| Line | Printed rate | Prototype | Receipt |
|---|---|---|---|
| Fire impact fee, residential per dwelling unit (sprinklered $458.68) fire | $464.60 per dwelling unit | $464.60 | Printed Effective 2026-05-01 Source · City of Bothell 2026 Impact Fees (updated 4/26), Fire fetched 2026-11-09, sha256 9b46e37f9903 |
| School impact fee, single family (detached dwelling unit), effective Jan 1 2026 school | $16,550 per unit | $16,550 | Printed Effective 2026-05-01 Source · City of Bothell 2026 Impact Fees (updated 4/26), School fetched 2026-11-09, sha256 9b46e37f9903 |
| School impact fee administrative fee per building permit school | $70 per building permit | $70 | Printed Effective 2026-05-01 Source · City of Bothell 2026 Impact Fees (updated 4/26), School fetched 2026-11-09, sha256 9b46e37f9903 |
| Park and open space impact fee, residential 2,000 or more sq ft (park $3,808.09 + open space $201.76) parks | $4,009.85 per dwelling unit by size | $4,009.85 | Printed combined total Effective 2026-05-01 Source · City of Bothell 2026 Impact Fees (updated 4/26), Park p.2 fetched 2026-11-09, sha256 9b46e37f9903 |
| Transportation impact fee, single family (ITE 210), effective May 1, 2026 transport | $13,387 per dwelling unit | $13,387 | Printed Effective 2026-05-01 Source · City of Bothell 2026 Impact Fees (updated 4/26), Transportation p.2 fetched 2026-11-09, sha256 9b46e37f9903 |
| Traffic impact additional administrative fee, 3% of the traffic impact fee admin · computed | 3% of traffic impact fee | $401.61 | 0.03 x $13,387 = $401.61 Effective 2026-05-01 Source · City of Bothell 2026 Impact Fees (updated 4/26), p.3 fetched 2026-11-09, sha256 9b46e37f9903 |
| Water facility charge, 3/4-inch (5/8) meter (includes SPU facility charge) water | $8,676 per 3/4" meter | $8,676 | Printed Effective 2026-05-01 Source · City of Bothell Public Works Fees 2026 (updated 5/26), Water Facility Charges fetched 2026-11-09, sha256 7ee9c02fd4ad |
| Sewer facility charge, single family, one Residential Customer Equivalent sewer | $5,984 per RCE | $5,984 | Printed; single family is one RCE per the King County Sewer Use Certification Form Effective 2026-05-01 Source · City of Bothell Public Works Fees 2026 (updated 5/26), Sewer Facility Charges fetched 2026-11-09, sha256 7ee9c02fd4ad |
| Storm drainage facility charge, citywide, one impervious surface unit (2,000 sf of new impervious surface) stormwater | $1,932 per impervious surface unit | $1,932 | Printed; one unit (2,000 sf impervious) assumed for the lot Effective 2026-05-01 Source · City of Bothell Public Works Fees 2026 (updated 5/26), Storm Drainage Facility Charges fetched 2026-11-09, sha256 7ee9c02fd4ad |
| Side sewer connection, single family tap | $350 each | $350 | Printed Effective 2026-05-01 Source · City of Bothell Public Works Fees 2026 (updated 5/26), Sewer Permits fetched 2026-11-09, sha256 7ee9c02fd4ad |
| Side sewer processing fee tap | $78 each | $78 | Printed Effective 2026-05-01 Source · City of Bothell Public Works Fees 2026 (updated 5/26), Sewer Permits fetched 2026-11-09, sha256 7ee9c02fd4ad |
| Building permit, $100,001-$500,000 tier: $1,514 for the first $100,000 + $9 per additional $1,000 or fraction, valuation $380,268 permit · computed | $1,514 for the first $100,000 + $9 for each additional $1,000 valuation | $4,043 | $1,514 + 281 x $9 = $4,043 on computed valuation $380,268 (ICC BVD R-3 V-B 175.92 x 2,000 + U V-B 71.07 x 400) Effective 2026-05-01 Source · City of Bothell Building Permit Fees 2026 (updated 12/25), Building Permit Fees table fetched 2026-11-09, sha256 fb2dbfbcede4 |
| Plan check fee, building permit fee x .65 permit · computed | .65 of building permit fee | $2,627.95 | 0.65 x $4,043 = $2,627.95 Effective 2026-05-01 Source · City of Bothell Building Permit Fees 2026 (updated 12/25), Plan Check Fee fetched 2026-11-09, sha256 fb2dbfbcede4 |
| Residential site review and inspection, new construction permit | $834 per permit | $834 | Printed Effective 2026-05-01 Source · City of Bothell Building Permit Fees 2026 (updated 12/25), Footnote 5 fetched 2026-11-09, sha256 fb2dbfbcede4 |
| Washington State residential building permit fee permit | $6.50 per permit | $6.50 | Printed Effective 2026-05-01 Source · City of Bothell Building Permit Fees 2026 (updated 12/25), Footnote 4 fetched 2026-11-09, sha256 fb2dbfbcede4 |
| Total listed | $59,414.51 |
Fee-change calendar
- None recorded
Need the full report for a parcel?
The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199
Delivered as a web page and PDF within 1 business day.
Watch this jurisdiction
Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.