Battle Ground, WA
Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.
Not included: Included: valuation permit, 65% plan review, state fee, new-home mechanical ($0.12/sq ft) and plumbing ($0.16/sq ft) permits on 2,000 sq ft heated, plot plan review, 3/4-inch meter and water SDC, sewer SDC (1 ERU), stormwater connection, and traffic, park and fire impact fees, all from the 2026 city fee schedule (inside city limits; outside is 1.5 times). Not included: school impact fees collected with the permit (Battle Ground School District $10,760; Hockinson $7,790; set by the districts), electrical permit (not found as a per-home line), 5/8-inch meter option, SDC/impact fee deferral fee, utility deposit and taxes. Searched 2026-11-09.
Water/sewer provider: City of Battle Ground (water, sewer, stormwater)
| Line | Printed rate | Prototype | Receipt |
|---|---|---|---|
| Building permit (valuation-based) permit · computed | $1,325 for the first $100,000 plus $9.09 for each $1,000 or fraction thereof, to and including $500,000 percent of valuation | $3,879.29 | Valuation $380,268 (ICC BVD R-3 V-B 175.92 x 2,000 + U V-B 71.07 x 400); 281 additional $1,000 units x 9.09 + 1,325 = 3,879.29 Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), Building Permits fetched 2026-11-09, sha256 9079dce9f767 |
| Building plan review permit · computed | 65% of permit fee percent of permit fee | $2,521.54 | 65% x 3,879.29 = 2,521.54 Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), Building Permits fetched 2026-11-09, sha256 9079dce9f767 |
| State building fee, residential permit | $6.50 flat | $6.50 | Printed Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), Building Permits fetched 2026-11-09, sha256 9079dce9f767 |
| New single family home mechanical permit permit · computed | $.12 per finished square feet per finished sq ft | $240 | $0.12 x 2,000 sq ft heated = 240.00 Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), Mechanical Permits fetched 2026-11-09, sha256 9079dce9f767 |
| New single family home plumbing permit permit · computed | $.16 per finished square feet per finished sq ft | $320 | $0.16 x 2,000 sq ft heated = 320.00 Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), Plumbing Permits fetched 2026-11-09, sha256 9079dce9f767 |
| Residential plot plan review permit | $70 flat | $70 | Printed Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), Land Use fetched 2026-11-09, sha256 9079dce9f767 |
| Water meter charge, 3/4-inch meter, city supplied and installed water | $539.07 per meter | $539.07 | Printed Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), Water Rates fetched 2026-11-09, sha256 9079dce9f767 |
| Water SDC connection fee, inside city limits, 3/4-inch meter water | $6,222 per meter | $6,222 | Printed; 5/8-inch meter is $4,150; 3/4-inch assumed for a single-family home Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), System Development Charge fetched 2026-11-09, sha256 9079dce9f767 |
| Sewer SDC connection fee, inside city limits, per ERU sewer | $15,701 per ERU | $15,701 | Printed; 1 ERU assumed for a single-family home Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), System Development Charge fetched 2026-11-09, sha256 9079dce9f767 |
| Stormwater drainage connection fee, per residence stormwater | $495 per residence | $495 | Printed Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), System Development Charge fetched 2026-11-09, sha256 9079dce9f767 |
| Traffic impact fee, single family transportation | $3,943.44 per dwelling | $3,943.44 | Printed Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), Impact Fee fetched 2026-11-09, sha256 9079dce9f767 |
| Park impact fee, single family parks | $4,538.31 per dwelling | $4,538.31 | Printed Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), Impact Fee fetched 2026-11-09, sha256 9079dce9f767 |
| Fire impact fee, single family fire | $1,018.78 per dwelling | $1,018.78 | Printed Effective 2026-01-01 Source · City of Battle Ground 2026 Fee Schedule (Resolution 25-12, effective 1/1/2026), Impact Fee fetched 2026-11-09, sha256 9079dce9f767 |
| Total listed | $39,494.93 |
Fee-change calendar
- None recorded
Need the full report for a parcel?
The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199