PadstakeFeesMoratoriaSite-work pricesMethodologyPricing

Terrell, TX

Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

$18,993.14listed total
Nonerank by 2025 new single-family permits

Not included: water and sewer taps and meter installation (collected at permit but no amount posted in a city document), irrigation permit, final plat fee ($265 per single-family lot, developer-level), utility deposit ($100) and connection fee ($35), school and other district fees. Roadway impact fee applies in four of five service areas (East area is $0); infill lots pay wastewater only. Building square footage assumed 2,400 (heated plus garage). Impact fees: Ordinance 3048, Schedule 2, effective Aug 31 2024 to Aug 30 2028. Building permit fees: Ordinance 3121, adopted Aug 26 2025.

Water/sewer provider: City of Terrell

LinePrinted ratePrototypeReceipt
Water impact fee, 5/8 x 3/4-inch meter (1.0 service unit)
water
$5,557 per service unit
per service unit, by meter size
$5,557Printed; 5/8" x 3/4" meter = 1.0 service unit equivalent (Ord. 3048 Exhibit 1)
Effective 2024-08-31
Source · Schedule 2 (p.32 of 32)
fetched 2026-11-07, sha256 56154fc769aa
Wastewater impact fee, 5/8 x 3/4-inch meter (1.0 service unit)
sewer
$4,890 per service unit
per service unit, by meter size
$4,890Printed; 1.0 service unit equivalent
Effective 2024-08-31
Source · Schedule 2 (p.32 of 32)
fetched 2026-11-07, sha256 56154fc769aa
Roadway impact fee, single-family dwelling (North, South, Southwest, West service areas; East area $0)
transportation · computed
$1,387 per service unit (vehicle-mile)
per vehicle-mile x vehicle-miles per dwelling unit
$4,466.141,387 x 3.22 vehicle-miles per single-family dwelling unit (Ord. 3048 Exhibit 1) = 4,466.14
Effective 2024-08-31
Source · Schedule 2 (p.32 of 32); service units in source 145 Exhibit 1
fetched 2026-11-07, sha256 56154fc769aa
New residential construction building permit
permit · computed
$2,900 up to 1,500 sq ft; $0.90 each additional sq ft
per square foot above 1,500
$3,7102,900 + (2,400 - 1,500) x 0.90 = 3,710.00 (2,400 sq ft assumed, heated plus garage)
Effective 2025-08-26
Source · Section 6.A.1
fetched 2026-11-07, sha256 8091de005463
Certificate of Occupancy
permit
$370
per certificate
$370Printed
Effective 2025-08-26
Source · Section 6.B.9
fetched 2026-11-07, sha256 8091de005463
Total listed$18,993.14

Fee-change calendar

Watch this jurisdiction