Red Oak, TX

Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

$17,731.48listed total
Nonerank by 2025 new single-family permits

Not included: boring costs, back-up inspection ($76.92 per address, if required), third-party review administrative cost, residential driveway approach ($50), sewer connection above $600 if actual cost is greater, utility deposits, school and other district fees. Impact fees are printed as maximum fees with no separate collected schedule (Resolution 24-072R rev. 8/12/2024); the 3/4-inch multi-jet row is used, the 5/8 x 3/4-inch row is lower. Building square footage assumed 2,400 (heated plus garage). Master Fee Schedule Resolution 25-087R rev. 12/23/2025.

Water/sewer provider: City of Red Oak

LinePrinted ratePrototypeReceipt
Water impact fee, 3/4-inch multi-jet meter (5/8 x 3/4-inch row is $3,200)
water
$5,530
per meter, by size
$5,530Printed (listed as maximum fee; no lower collected schedule printed)
Effective 2024-08-12
Source · Chapter 13.00 Impact Fees, Resolution 24-072R
fetched 2026-11-07, sha256 9129d8bb323f
Wastewater impact fee, 3/4-inch multi-jet meter (5/8 x 3/4-inch row is $3,550)
sewer
$4,400
per meter, by size
$4,400Printed (listed as maximum fee)
Effective 2024-08-12
Source · Chapter 13.00 Impact Fees, Resolution 24-072R
fetched 2026-11-07, sha256 9129d8bb323f
Roadway impact fee, single-family detached (service areas 1 and 2 same rate)
transportation · computed
$868.00 per service unit (vehicle-mile)
per vehicle-mile x vehicle-miles per dwelling unit
$4,001.48868.00 x 4.61 vehicle-miles per dwelling unit (ITE 210, Roadway Impact Fee Study Aug 2023 Table 2.13 LUVMET, source 182) = 4,001.48
Effective 2024-08-12
Source · Chapter 13.00 Impact Fees; rate from schedule, veh-mi from study
fetched 2026-11-07, sha256 9129d8bb323f
Park improvement fund fee, single-family
parks
$700.00 per dwelling
per dwelling
$700Printed
Effective 2025-12-23
Source · Sec. 5.003(d) Park improvement fund
fetched 2026-11-07, sha256 f569e3a67703
Single-family construction plan review and inspection (one-permit new construction)
permit · computed
$0.75 per square foot under roof
per square foot under roof
$1,8002,400 sq ft (heated plus garage) x 0.75 = 1,800.00
Effective 2025-12-23
Source · Sec. 5.003(a)(1)(A)(iii)
fetched 2026-11-07, sha256 f569e3a67703
Certificate of Occupancy
permit
$50.00
per certificate
$50Printed
Effective 2025-12-23
Source · Sec. 5.003(c)(1) Miscellaneous construction fees
fetched 2026-11-07, sha256 f569e3a67703
Water connection, 5/8 to 3/4-inch (includes meter box and meter)
water
$650.00
per connection, by size
$650Printed
Effective 2025-12-23
Source · Sec. 5.003 Water connection
fetched 2026-11-07, sha256 f569e3a67703
Sewer connection
sewer
$600.00 or actual cost, whichever is greater
per connection
$600Printed minimum $600.00
Effective 2025-12-23
Source · Sec. 5.003 Sewer connection
fetched 2026-11-07, sha256 f569e3a67703
Total listed$17,731.48

Fee-change calendar

Watch this jurisdiction

Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.