Prototype: 2,000 sq ft single-family detached, 3 bed / 2 bath, 3/4-inch water meter, 400 sq ft garage.

Impact fees verifiedno total: permit and tap fees not posted
Nonerank by 2025 new single-family permits

Impact fees verified. Not a full total. Columbia TN (CPWS): water impact fee $6,000 for a 3/4-inch meter (July 1, 2026), new water service fee ($300 + $440 per SFU, 1 SFU) and 3/4-inch meter fee for a residential request of 3 lots or fewer; application fee $0. NOT included: sewer connection (City of Columbia, separate sewer service charges PDF not read), building permit fees (not found), 4+ lot developer rates. Page never shows a total. 2026-11-09 second pass.

Water/sewer provider:

LinePrinted ratePrototypeReceipt
Water impact fee, 3/4 inch meter
impact
$6,000
per 3/4 inch meter, July 1, 2026 (projected 2027 $6,500; 2028 $7,000)
$6,000Printed
Effective 2026-07-01
Source · CPWS New Water Service Process, Developer Fee table and Impact Fee Schedule (July 1, 2026 column), Residential (3 lots or less)
fetched 2026-11-09, sha256 33ed0334eaac
New water service fee, residential (3 lots or less)
water · computed
$300 plus $440 per *SFU
per single family unit equivalent
$740$300 + $440 x 1 SFU = 740
Effective 2026-07-01
Source · CPWS New Water Service Process, Developer Fee table and Impact Fee Schedule (July 1, 2026 column), Residential (3 lots or less)
fetched 2026-11-09, sha256 33ed0334eaac
Meter fee, 3/4 inch
water
$1,000 per 3/4" meter
per 3/4 inch meter
$1,000Printed
Effective 2026-07-01
Source · CPWS New Water Service Process, Developer Fee table and Impact Fee Schedule (July 1, 2026 column), Residential (3 lots or less)
fetched 2026-11-09, sha256 33ed0334eaac

Fee-change calendar

Need the full report for a parcel?

The Site Cost Report adds the parcel's water and sewer provider, capacity notes and nearby site-work prices. Buy this report, $199

Delivered as a web page and PDF within 1 business day.

Watch this jurisdiction

Get an alert when this fee schedule changes, a future increase is adopted, or a capacity notice starts, changes or lifts. Alert delivery opens with the paid plan; your signup is stored now.